Successful trade fair showcases the added value of BIM in prefabricated projects

On 27 October 2022, bouwBIM organised a prefab trade fair with the aim of bringing together all potential members of the construction team, including prefab manufacturers, in an interactive way. Need we say more? This was an event to look forward to.
Christophe Van der Gucht, managing director of Bouwpunt Van der Gucht and founder of bouwBIM: “The first edition brought together various prefab partners, each demonstrating in their own way how BIM models can help improve efficiency on site. The construction sector is slowly but surely realising that investing more time in thorough preparation significantly reduces the margin for error on site. We were therefore delighted to welcome many architects, contractors, engineering consultancies, prefab manufacturers and other construction professionals to our trade fair.”

Productivity, efficiency and proactivity
Christophe Van der Gucht: “It will hardly have escaped anyone’s notice, but recently the price of every tender has risen considerably. This is obviously due to increases in the cost of the materials required, but labour costs have also gone through the roof. And that is precisely what we can address. Not by using cheaper labour, and preferably not by accepting lower margins either. What we can improve is productivity, efficiency and proactivity. BIM has already proved itself in this respect as a way of working together and forming partnerships that significantly increase efficiency on site. By not only designing the project, but also adapting and streamlining existing processes, you save time and boost returns during the construction phase.”

Services for prefabrication
1. Helping to optimise projects
What can be prefabricated, what is required and how can that level be achieved? Taking a fresh look at the project brings to light possibilities that may not yet have been considered. The earlier this process begins, the more opportunities there are for optimisation. Ideally, bouwBIM joins during the preparation phase, but advice can also be provided during the design phase.
2. Assistance with managing the CDE (Common Data Environment)
With Trimble Connect as the CDE, all construction team partners can work together and share and consult information. Trimble-approved training is also provided to teach users how to use the platform or find the best way to collaborate.
3. Coordination of digital information flows and models
When a prefab manufacturer supplies a model, it is advisable to integrate it into the project’s own model. This brings errors or potential problems on site to light, allowing them to be corrected before elements go into production. This saves costs during construction. bouwBIM incorporates models supplied by manufacturers or subcontractors into its own model to carry out clash detection. This includes, for example, correctly coordinating and positioning the elements, linking information to elements, checking dimensions, identifying clashes with other elements, missing or incorrect openings for service penetrations, and errors in wet joints or reinforcement connections.

Shared responsibility
“We must take shared responsibility and not simply carry on because we have been doing things the same way for years. The solution is to put together fully integrated construction teams. That is the only way to make one another truly more efficient. To do so, involve all the different parties in every project as early as possible. With bouwBIM, all data can be integrated and everyone perfectly coordinated. An efficient process saves not only time, but money too,” concludes Christophe Van der Gucht.