1,274 driven piles for new prison

The foundation piles for the new prison in Dendermonde were installed by De Waal Solid Foundations. “As there were no structures near the complex to be built, and the site investigation results were suitable, we opted for precast driven piles,” explains CEO Olivier Rens.
The choice of precast driven piles is noteworthy. “This system is now rarely used in Belgium because noise and vibration are usually unacceptable. The long lead time for these piles can also present challenges. That is a shame, as this type of pile generally delivers very satisfactory results. Driving preloads the piles, resulting in less settlement than with screw piles. The amount of concrete entering the ground is also limited, and there is no concrete waste on site. We began installing a total of 1,274 piles in September 2020. They are 8 to 10 metres long and have a load-bearing capacity of 400 to 1,000 kN. The work took 25 working days using two machines,” says Olivier Rens.

Unprecedented speed
De Waal Solid Foundations has a rich history, which began when De Waal Palen was founded in 1959. It started out as a division of its Dutch parent company, De Waalpaal bv, and was mainly active in driving precast piles. But that was by no means the end of the story. In 1987, then director Frank Poorteman took over the reins of the Belgian division. During this period, the company, headquartered in Lokeren, developed an innovative system of double displacement screw piles: a completely vibration-free system that does not bore soil out of the ground. These piles come in two types: the gvs pile, a screw pile with a smooth cylindrical shaft that is ideal for drilling deep into relatively hard sand layers, and the helical pile, with a helical shaft, perfect for friction piles.
The advantages are clear. The system is completely vibration-free, produces no excavated soil to be removed, and the piles have a high working load capacity despite their relatively small diameter. It also made reinforcement along the full length possible. It was a success from the outset. Using machines specially developed for the system and concrete pumps, piles could be installed at unprecedented speed. This success also extended internationally …

Complete solutions and first-class service
Over the years, this pile type has become the company’s main activity. Projects have been carried out in Belgium, Luxembourg, the Netherlands and northern France. The fleet of machines for installing tubular piles has also been expanded, making it possible to provide solutions inside existing buildings. Following several acquisitions, the opening of a branch in Poland and a merger in 2017, De Waal Solid Foundations can offer a complete solution for construction pits and deep foundations, backed by first-class service.
Olivier Rens: “As the number of projects and techniques increased, and our activities became more widely spread across Belgium, the Netherlands, France, Poland and Romania, the need arose to create a single central organisation. The merger was therefore intended to further optimise our services. Mission accomplished!”