A ‘high-rise’ school on an Antwerp brownfield site

Per verdieping hebben we gemiddeld achttien werkdagen nodig”, zegt Tim D’haese. (Beeld: Tim D’haese)
Per verdieping hebben we gemiddeld achttien werkdagen nodig”, zegt Tim D’haese. (Beeld: Tim D’haese)

One of the first new-build projects in the former Petroleum Zuid logistics zone along the Scheldt in Antwerp is a school for secondary technical education. With a floor area of 10,717 m², it is one of the largest new school construction projects in Flanders.

When completed, in spring 2022, the school is set to accommodate the 290 pupils of the existing city schools for part-time and adult education, CDO Werkend Leren Antwerpen Zuid and CVO Encora. This will bring the ‘hard technologies’ courses offered by both schools together on a single technical campus, while addressing the shortage of available workshop space.

At almost 35 metres, the complex is unusually tall for a school. In addition to classrooms, subject rooms, technical rooms and other spaces, it will include a range of other facilities. An open-air playground will be created on the sixth floor, while Antwerpse Bouwwerken is building a sandpit on the third floor. “It may seem unusual for a secondary school, but this sandpit is not for recreation. It will serve as a training area for installing sewers and other underground utilities,” explains site manager Tim D’haese. Other technical facilities for training include a vehicle lift for automotive technology, a welding installation and a simulated stacker warehouse.

Two sets of technical systems

“This and other teaching infrastructure meant that, from a technical perspective, we had to combine two different concepts,” explains the site manager. “On the one hand, there is the technical equipment needed to operate the building, such as heating and ventilation. On the other, there are all the basic systems needed for the courses. These include installations for welding, plastering and woodworking, as well as, for example, working with forklift trucks. The structure must therefore not only support heavy loads, but also withstand significant impacts.”

The concrete load-bearing structure is clad externally with aluminium panels.
Tim D’haese, site manager at Antwerpse Bouwwerken.

Work began in August 2020 and is due to be completed in May 2022. The building rests on a foundation of 300 piles. “We need an average of 18 working days per floor. The foundations and ground floor were already completed in October 2020,” says D’haese. The load-bearing structure comprises columns, beams, precast wall panels and lattice girder slabs. Both prestressed hollow-core slabs with structural topping and ready-mix concrete were used. The stairs were delivered as finished precast concrete units. “We worked with mixed teams so that no one was permanently assigned to just beams or columns. This approach also prevents frustration. Teams specialising in one area do not have to wait for another team to finish the previous stage.”

Much-loved concrete blocks

The façade is finished partly with aluminium cladding and partly with bonded, split-face concrete blocks. “The architects specifically requested that the concrete blocks be split to create a rough appearance. The windows are fitted with aluminium frames and the associated solar shading. The specialist rooms have polished concrete floors, the sanitary areas are tiled, and the external façades are clad in aluminium.” As acoustics are a key consideration in a school with noisy practical courses, most ceilings have been coated with acoustic spray plaster. The shell works used a total of 377 columns, 412 beams, 27,840 litres of grout, 6,600 m² of concrete masonry, 280 tonnes of masonry mortar, 8,000 m² of power-floated concrete and 75 flights of stairs and landings. The hollow-core slabs cover a total floor area of 8,000 m², while the lattice girder slabs cover 1,500 m².

3D plans for everyone

During the design phase, it was decided to model the entire project in BIM. “One of the key benefits is that clashes between different building services can be identified and resolved during the design phase. This keeps construction errors and the associated costs of rework to a minimum,” says D’haese. “During construction, we used a highly visual interface so that foremen, workers and tower crane operators could also plan and review their work using 3D plans with clear colour coding.” 

PROJECT DETAILS

Client
DBFM Scholen van Morgen (Brussels)
Architect
POLO Architects (Antwerp)
Main contractor(s)
Antwerpse Bouwwerken (Antwerp)

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectConstruction projects
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.