A landmark for Blankenberge

Text Anastasia VerleysenImage Van Tornhaut en A1AR

A landmark for Blankenberge

On Ruzettelaan in Blankenberge stands one of the few high-rise buildings on the Belgian coast. The location is not the only thing that makes ‘The One’ special. The apartment building, with 89 units, is unique in many respects, and even features a construction innovation that has since been adopted in other projects across the country.   

The One was built on a triangular site, where dunes meet the polders, at the junction of two roads. “This is where the town of Blankenberge begins when you arrive from the direction of Zeebrugge. In that respect, this residential development is a landmark for Blankenberge,” says architect Nele Boussemaere of A1AR. “The RUP allowed us to build higher than usual. This is on the seafront. The views we wanted to offer from the apartments had to go beyond a standard window with a sea view. We achieved wide-ranging views by cutting into the building’s volume, making it possible to give every unit corner windows with sweeping views of the sea and/or polders. The slender building rises almost directly from the dunes. The balconies alternate, adding dynamism to the façade and giving every resident a high-quality terrace. ‘It is not a monolithic block, which would not do justice to the location,’ says Nele Boussemaere. ‘The rounded corners give the building a softer appearance and follow the contours of the dune landscape. We also incorporated the dunes and polders into the landscaping, designed by Atelier Artisjok.’

The podium is seven storeys high. Storeys eight to eleven are more slender and effectively divide into two towers.

Render instead of concrete

Van Tornhaut, a class 7 construction company based in Aalter, started work on 1 April 2019. “The original plan allowed 1,000 working days for fifteen storeys. Commercially, that is not attractive,” says lead project manager Jonas De Brouwer. “We cut that to 600 days. That was optimistic, especially given the weather delays on the coast. But we met the target comfortably, despite the coronavirus period, when shutdowns at concrete plants made it difficult to get concrete. That was just when we were working on the basement levels.”

The basement comprises three levels built with concrete, reinforcing steel and structural steel. Concrete was also used in the rest of the structure, with calcium silicate masonry on the top floors. For the horizontal bands between the facing brickwork and for the terraces, the choice was render with a concrete look. “That helped us speed up the construction phase,” says Jonas De Brouwer. “The windows and doors are made of black anodised aluminium. All the windows ordered off-plan were delivered on site, allowing us to make and finish one floor wind- and watertight while working on the next. That also helped us work faster.” 

Rounded, staggered terraces give the building a softer appearance.

A first for technical service risers

The coastal location called for specific criteria and additional design work, including for the terrace balustrades. “The curved glass had to be fitted on the inside of the concrete-look terraces, while still allowing sufficient ventilation and preventing water or sand from getting in. To achieve the desired appearance, we used a film in the glass,” says Nele Boussemaere. “Van Tornhaut built a full-scale mock-up of the terraces on site to check whether our ideas would work in practice.”

The One also boasts a Belgian first in its technical service risers. “They were prefabricated by Decat in sections of three storeys and then connected. We are seeing this approach more and more. It requires fewer working hours and allows work on site to progress faster. The connections are also easier to control in a factory setting, which means fewer errors,” says Jonas De Brouwer. “The high-rise aspect is also unusual for our country. We encountered complex regulations that the authorities involved often struggled to interpret, such as those governing dewatering. This has now become very important, but it was not the case when the planning application was submitted in 2017. Due to stricter dewatering regulations, a 14-metre-deep CSM wall and a base plug at the same depth had to be installed to make the excavation watertight. The base plug is essentially a concrete slab that seals the bottom of the excavation. This process has a major impact on the construction programme. The One was a project that took a great deal of work, but all the partners involved can be proud of the result.”    

Question about this story? Ask your question

Who worked on it

The One in Blankenberge

  1. clientVolus
  2. architectA1AR architects & more
  3. main contractorVan Tornhaut
  4. technische kokersDecat
  5. landscapingAtelier Artisjok
  6. kitchensMAPE

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectThe One
  • SubjectConstruction projects
  • CompanyVolus
  • CompanyA1AR architects & more
  • CompanyVan Tornhaut
  • CompanyDecat
  • CompanyAtelier Artisjok
Share this article

Advertisement

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.