Het dak van 650 m² was een moeilijke constructie met inwendige terrassen en zinken afwerkstukken.
Het dak van 650 m² was een moeilijke constructie met inwendige terrassen en zinken afwerkstukken.

Dunehotel is a new eco-hotel in a prime location. It is set in the vast dune landscape of Nieuwpoort-Bad, 150 metres from the beach. Guests are immersed in an atmosphere of warmth, comfort and luxury. It is clear that this is a new jewel on the Belgian coast.

CIT Blaton is a family business with 155 years of experience and an impressive portfolio of projects. “We have built many hotels in Belgium, which is why the client asked us to deliver Dunehotel,” says Jan Heyde, project manager at CIT Blaton. “DUNEHOTEL nv had produced some excellent digital images. Our task is to translate them into reality in a technically sound, high-quality way.” The project had to comply with the spatial implementation plan. This stipulated not only the maximum building height, but also the appearance of the building: a white façade and pitched roofs with red roof tiles. “The 650 m² roof was a complex structure, with internal terraces and zinc detailing. It was a technical challenge, and we also had to take account of fire spread.”

CIT Blaton also had to consider groundwater control when building the hotel. Groundwater levels in the adjacent dune area were not allowed to rise or fall by more than 10 centimetres. “To limit the impact of groundwater drawdown outside the excavation pit, we opted for a closed cofferdam with a soil-mix wall. We installed CSM walls to a maximum depth of 19.5 metres, reaching the natural impermeable layer. Throughout the project, we held constructive discussions with the Agency for Nature and Forests. We sent them weekly project reports. Honest, direct communication makes execution easier.”

Because of the wind risk, the tower crane serving the underground car park stood 60 metres high.

Wind tunnel analysis

For tall buildings, or buildings in exposed locations such as the coast, it is advisable to commission a specialist wind tunnel analysis. This helps prevent wind nuisance and even dangerous wind conditions. It is important to factor this in during construction, says Jan Heyde: “The rooftop plant is additionally anchored. Everything is airtight, and all the drains have large sand traps. The wind study found that the surrounding buildings could create whirlwinds. That is why the tower crane serving the underground car park stood 60 metres high, which is unusual. The crane for the hotel itself was 43 metres high. All our cranes can lift 7,000 kilograms at a radius of 40 metres.”      

Dunehotel is set amid the dunes of Nieuwpoort.

Investing on the Belgian coast

With a total floor area of 9,800 m², Dunehotel has 88 rooms and offers the luxury of a four-star hotel. Rooms at the rear enjoy beautiful views of the dunes. Those at the front overlook an attractive green park, which is being redeveloped by the city of Nieuwpoort. Each room is being sold to investors for a starting price of 175,000 euros. The investment guarantees a return of 3.25 per cent for thirty years. Investors also have no repair or maintenance costs and can stay in their own hotel room for two weeks.

Plans for the two lower floors of Dunehotel are still being finalised. “We know that the front section will be used as an underground car park,” says Jan Heyde. “These floors also have views of the dunes at the rear. Level -1 is most likely to house the restaurant, with the option of using the space for meetings or exhibitions, while level -2 will be a multifunctional meeting room.” The new hotel welcomes not only business travellers, but also tourists looking to enjoy the diversity of the Belgian coast in complete luxury.

Question about this story? Ask your question

Wie aan Dunehotel werkte

  1. clientDUNEHOTEL nvIn this story
  2. architectCIT BlatonIn this story
  3. main contractorVauterin: Thirry & partnersIn this story
  4. clientSea CoastMentioned in The challenges of building in a coastal town
  5. grondwerkersMichael BoonMentioned in The challenges of building in a coastal town
  6. binnenschrijnwerkSchrijnwerkerij BorraMentioned in The challenges of building in a coastal town

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectDunehotel
  • SubjectConstruction projects
  • CompanyDUNEHOTEL nv
  • CompanyCIT Blaton
  • CompanyVauterin – Thirry & partners
Share this article

Advertisement

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.