Aperam machine hall, Genk | World-renowned steel producer expands with imposing machine hall

Anyone familiar with the steel industry knows that Aperam has ambitious plans. The listed company produces high-quality stainless steel sheets at its factory in Genk and has built an international reputation over the years. To further strengthen its formidable reputation, Aperam is modernising its production unit with a brand-new cold rolling mill (CRM5) and an annealing and pickling line (BUL4). Contractor ASK Romein is building the steel main structure of the machine hall to a very tight schedule, making it fully weatherproof.
Aperam is a global player in stainless steel and operates a factory in Genk that runs 24/7. Aperam’s production unit is a showcase for modern technology, with a brand-new annealing and pickling line and a new cold rolling mill in the pipeline to replace older installations. ASK Romein plays a crucial role in both projects, known respectively as BUL 4 and CRM 5. The renowned industrial construction specialist from Malle is currently completing the main structure of the sophisticated machine hall for BUL 4 and will start work on CRM 5 in September. “For BUL 4, we are responsible for building the steel supporting structure and the building envelope of the new machine hall, making it fully weatherproof,” says project manager Tom Vroon.

The supporting structure of the imposing machine hall was completed in less than six months.
Specific design
The new Aperam machine hall is an unusual building, to say the least. The long hall consists of four sections with a total length of 400 metres and is 19 metres wide. Its main structure accounts for around 4,700 tonnes of steel and is made up of HL1000 sections. “To optimise the structure, we opted not for lattice columns but for large, single-piece columns, stacked on top of one another in the three-storey section. Floor beams between them complete the main structure,” explains Tom Vroon. “It is important to know that overhead cranes will be installed on every floor, ten in the entire building, and that each level has a specific function. So we have not simply put up a large box. On the contrary, each section required a specific design to accommodate the successive processing stages that the stainless steel sheets will undergo.”
Unusual schedule
It goes without saying that projects on the scale of BUL 4 are far from routine. It is also the first time that ASK Romein has worked for Aperam. “The sheer size of the machine hall speaks for itself, but we also had to work to very tight tolerances,” says Tom Vroon. “Another unusual aspect was that we had to follow an atypical schedule to complete the shell within the extremely tight construction period. Another contractor carried out foundation work from 7 am to 15 pm, after which we installed the
steel structure between 14 pm and 22 pm. This enabled us to erect the supporting structure for the entire hall in less than six months. Needless to say, this called for a specific approach, not least because the work had to be done in the depths of winter. For example, we installed numerous floodlights in advance to ensure safety at all times and keep work moving smoothly in the dark. There were also always two safety coordinators on site to keep everything running smoothly. We are currently finishing the façade. In August, we will put the finishing touches to it, after which we will start building CRM 5, the new cold rolling mill.