BlueChem, Antwerp | BREEAM Excellent rating for new incubator

With 3,300 m² of workspace and eighteen laboratories, BlueChem is the first property development on the climate-neutral Blue Gate Antwerp business park. “From the outset of the design, we modelled the building services in 3D. The entire project was then designed using BIM,” explains project manager Kurt Schrauwen, speaking about this distinctive Design & Build contract.

The building is a model of sustainability.
BlueChem gives start-ups in sustainable chemistry access to infrastructure, financial support and a network of experts. The partners aim to help innovations scale up to industrial level more quickly. BlueChem is a collaboration between public-sector organisations, industry and knowledge institutions. The complex can accommodate around twenty companies. In spring 2020, the first start-ups moved into this new hub for sustainable chemistry: Calidris Bio, IBEVE, Peace of Meat and Triple Helix.

Kurt Schrauwen: “Despite the tight schedule, we finished well within the planned timeframe. We started work on the foundations in December 2018 and handed over the project in February 2020.”
Four stars for sustainability
The contract to build BlueChem’s home was awarded to MBG, based on designs by LOW architecten, Ingenium and eld. How does this project differ from MBG’s many other projects? “First, the building has a BREEAM Excellent rating: that means four stars, the second-highest rating. Sustainable choices had to be made in every aspect of the building,” says project manager Kurt Schrauwen. These include a heat recovery ventilation system, a connection to the BlueGate district heating network and an energy recovery system for the lift. The building materials carry EPD and FSC sustainability labels, the water supply circuits are fitted with leak detection, and the lighting is smart and therefore energy-efficient. In addition, all the building services are connected to a building management system.

BlueChem can accommodate around twenty start-ups in sustainable chemistry.
A technical tour de force
“Alongside sustainability, the building’s function presented an additional challenge. The eighteen laboratories require a lot of technical features. There was also a need for sufficient ventilation capacity. We laid everything out neatly and logically in our design. Most of the labs are on the lower floors, with most of the offices at the top of the building. Two large risers serve all the labs. On the top floor, we created a covered area for all the building services: air handling units, cooling, reheating coils … For our tender, we carried out an extensive study of these systems and developed everything in 3D to give a clear picture.”

All the building services are housed under cover on the top floor.
BIM authority
MBG developed BlueChem entirely in BIM. It has a BIM team dedicated to advising project managers on BIM and ensuring that the plans from all suppliers are brought together in a single shared model. In recent years, MBG has built up considerable BIM expertise through the construction of AZ Sint-Maarten in Mechelen and Gare Maritime at the Tour & Taxis site in Brussels. Kurt Schrauwen: “BIM is a collaborative model that ensures everyone involved in the construction process works with the same information and plans. Setting up such a model takes time, but you more than make that investment back later because the construction process runs more smoothly, there are fewer errors and checks afterwards are much quicker. Despite the tight schedule, we also finished BlueChem well within the planned timeframe. We started work on the foundations in December 2018 and handed over the project in February 2020.”

The entire project was modelled in BIM.
Nobody gets hurt
Under the motto ‘nobody gets hurt’, MBG enforces an exceptionally strict safety policy on all its projects. The construction company was once the first in Belgium to obtain VCA certification. After all these years, safety remains firmly at the top of the list of priorities. Kurt Schrauwen: “We hold a kick-off meeting with every subcontractor we appoint, with safety as a crucial item on the agenda. We regularly organise toolbox talks on site: before workers start work, we briefly discuss an incident or a point of attention. We also have an app for quickly reporting safety incidents or recording reports from safety walks. This means safety does not have to involve a lot of paperwork.”
Question about this story? Ask your question
Who worked on it
BlueChem in Antwerpen
- contractorMBG
- architectLOW architecten
Keep following this
Get an email when a new story is published. No account needed.
- ProjectBlueChem
- SubjectConstruction projects
- CompanyMBG
- CompanyLOW architecten