Brownfield transformed into a new municipal hub

Text Koen MortelmansImage Cordeel en Luc Vilain/communicatiedienst Kapellen

De gevels van de assistentiewoningen zijn afgewerkt met steenstrips.
De gevels van de assistentiewoningen zijn afgewerkt met steenstrips.

At the end of 2022, staff at the municipality of Kapellen in Antwerp moved into three new buildings in the heart of the municipality. Since then, with the exception of the library and swimming pool, Kapellen residents have been able to access all municipal services at a single location.

Before work began, the site was not exactly the most pleasant place in the municipality. With a former industrial laundry, a gymnasium once converted into a function room and an ageing service centre, it was a typical brownfield site. In addition, the ground was heavily contaminated in some places, so dewatering the excavation required a return-flow system with filters. As soil remediation proved time-consuming, construction work had to be carried out at a rapid pace.

“Bruggeske is one of three sites in the centre of the municipality being redeveloped in accordance with a master plan,” says project architect Dirk Liekens (Architecten Achtergael). “The overall programme comprises public, residential and, to a limited extent, commercial uses.” In addition to two new municipal buildings, two buildings containing a total of 69 assisted-living flats for Zorgbedrijf Vlaanderen have been constructed, along with a service centre, a job shop and a travel café. The project required a carefully planned administrative and legal process, under which contractor Cordeel carried out the construction works under a building lease on land owned by the municipality. Architecture firm Achtergael, main contractor Cordeel and the municipality worked together using a construction team model.

The brownfield in the heart of the municipality has been put to good use.

Best available techniques

 The best available techniques and technologies have been incorporated into the project. Solar panels have, of course, been installed on the roofs. The buildings are also connected to an aquifer thermal energy storage (ATES) system for heating and cooling. The system uses groundwater at a depth of around 60 metres. The water is pumped through a heat exchanger in a closed circuit. In summer, the temperature difference provides cooling for the buildings, while in winter it is used for heating. The sustainable approach is also reflected in the materials, with plenty of timber and large areas of glazing to maximise natural daylight.

No place for car enthusiasts.

Intensive green roof

“The area above the underground car park has been laid out as an intensive green roof,” emphasises Bart Audenaert, project manager at construction company Cordeel. “The build-up is up to 1.2 metres thick. This meant that the concrete slab above the underground car park had to be heavily reinforced and is up to 1 m thick in some areas to support the additional weight.” Prefabricated concrete elements were used predominantly for the upper levels. “They came from our own production facility in Temse,” says Audenaert. “They form a load-bearing shell, which we finished with an insulation layer and façade slips.”

The administrative centre is a detached building, with the various services and workspaces arranged around a central courtyard. 

It has a curtain wall with a timber lattice structure. This structure enhances staff privacy. A cantilever that gives the building its distinctive form emphasises the entrance. The ground floor consists mainly of the entrance area, with service counters arranged around the central courtyard to create a clear layout for visitors. The supporting back offices are located directly behind the counters. These workspaces are laid out as open-plan offices, divided into smaller work areas and departments by carefully positioned spaces, including focus rooms and printing areas. The upper floor accommodates the mayor and aldermen’s board, as well as offices for support services. 

New workspaces for municipal staff.

Traffic-calmed

Cars are not welcome on the site. Its permeable layout allows pedestrians and cyclists to move safely through Bruggeske itself and the wider surrounding area. Below ground, however, there is a largely public car park with 125 spaces and a private section with 45 spaces. The municipal archive storage area and changing rooms for technical staff are also located underground.  

A wide range of kitchen equipment.

Question about this story? Ask your question

Who worked on it

Bruggeske in Kapellen

  1. clientgemeente Kapellen
  2. clientZorgbedrijf Vlaanderen
  3. architectArchitecten Achtergael
  4. main contractorCordeel
  5. interior finishingTecnospace
  6. keukenapparatuurSabemaf

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectBruggeske
  • SubjectConstruction projects
  • Companygemeente Kapellen
  • CompanyZorgbedrijf Vlaanderen
  • CompanyArchitecten Achtergael
  • CompanyCordeel
  • CompanyTecnospace
Share this article

Advertisement

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.