Initium is one of the latest construction projects in Antwerp’s revitalising station district. At one of the corners of the five-way junction where Plantin- en Moretuslei meets several other streets, an apartment building incorporating a hotel has been constructed, integrating seamlessly into the surrounding urban fabric.

Plantin- en Moretuslei is one of the main routes into the city centre. Most of the existing buildings date from the period between 1890 and 1940, with a significant number in the Art Deco style. However, the site in question had lain vacant for more than thirty years, so a substantial amount of overgrown vegetation and debris had to be cleared before construction could begin. A small quantity of contaminated soil also had to be removed for remediation.

Following a land swap with the project developer, the City of Antwerp further chamfered the already slightly clipped corner to create extra space for the tram to cross the junction and to provide a small area of public space. This did, however, limit the architects’ design options. As the new tram track had already been laid before work on Initium began, it also imposed strict logistical constraints on contractor MBG. “We were temporarily given the use of part of a traffic lane during the works, but at 25 by 3.5 metres, it was still very tight when pouring concrete,” recalls project manager Stefan Paredaens. “And the small units severely limited the scope for storing materials inside the building. Fortunately, we had more room once the roof over the ground-floor inner area was in place.”

The façade articulation gives Initium a dynamic appearance. (Image: Binst Architects)

Stepped residential terraces

The architects had to take account of the difference in building heights between the relatively monumental Plantin- en Moretuslei and the much more modest Provinciestraat. “That is why we conceived the new complex as a series of stepped residential terraces, with a façade articulated in a sawtooth pattern and folded like a kind of screen,” explains Robert Osinga, project architect at Binst Architects. “Along both streets, we built against the existing party walls to complete the urban fabric as effectively as possible.”

“To complement the nearby area, which is protected as a townscape, we opted for large-format facing bricks, measuring almost 30 by 5 cm. Their light colour harmonises with the sandstone used on neighbouring buildings. We laid the bricks without vertical joints, making the horizontal bed joints more pronounced. We also added an accent course at each level, in the form of profiled floor bands in architectural concrete, in a tone-on-tone shade that matches the brickwork. Polishing the concrete brought out the aggregates and further enhanced the façade’s mineral character.” The dark-coloured external joinery is combined with expressive, detailed railings.

The hotel section along Plantin- en Moretuslei rises nine storeys. “The hotel has seventy rooms. Its height matches that of the neighbouring Arass Hotel & Business Flats perfectly. The new hotel is partly designed for extended stays, so several rooms are equipped with a substantial basic kitchen setup.”

The kitchen facilities make a number of hotel rooms suitable for extended stays. (Image: Adagio Aparthotel )

A rich living experience

The tallest volume, containing apartments on the corner, has ten storeys. Its added height is expressed as a crown, with duplexes on the top two levels. The mix of apartments is aimed primarily at first-time buyers. “This could create a kind of cross-pollination with the hotel. There are eight studios, 48 one-bedroom apartments, ten with two bedrooms and just two with three bedrooms. Their floor areas range from 50 to 130 m². Additional spaces for shared experiences are the basis for a rich living experience: a communal garden with a relaxation area, a gym, a laundry room and 400 m² of commercial space at ground-floor level. The hotel immediately took up most of this space to accommodate its breakfast room, ensuring an active presence and interaction with the surroundings from the outset.” The largely glazed ground-floor frontage is articulated by robust concrete piers carried down from the upper storeys. These piers use the same material as the concrete floor bands.

The building’s stepped, articulated form means that each of the three apartment sections has its own kind of ‘community’. “An extensive green roof will be installed on the roof of each section, while the roof over the fully built-up ground floor will be an intensive green roof.”

Plantin- en Moretuslei is one of the main routes into the city centre. (Image: Binst Architects)

Grid pattern

The hotel’s external joinery and brickwork follow a clean, precise grid. “Here, we combined grey facing brick with dark-coloured aluminium external joinery. To enhance the façade’s expression, we set the windows back. This enabled us to give the hotel rooms narrow balconies,” explains Robert Osinga.

“We built the hotel’s internal walls in calcium silicate block and plasterboard,” says Paredaens. “In the apartments, we used calcium silicate block and gypsum blocks. This improves acoustic insulation. The hotel also specifically requested fitted carpet for the corridors. The room floors are finished in PVC. Importantly, the window reveals are also acoustically insulated, and every room has a door with high acoustic insulation. Mathieu van der Poel can stay here with peace of mind.” Buyers of the apartments could choose an individual finishing package according to their budget.

The communal bicycle storage for 194 bicycles is on the ground floor, while parking for 97 cars is spread over two underground levels. “We positioned the car park entrance and exit as far from the junction as possible to minimise any potential disruption in either direction,” says the project architect.    

Question about this story? Ask your question

Who worked on it

Initium in Antwerpen

  1. ClientCandor
  2. ArchitectBinst Architects
  3. Main contractor(s)MBG

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectInitium
  • SubjectConstruction projects
  • CompanyCandor
  • CompanyBinst Architects
  • CompanyMBG