Copernicus, Brussels | Elegant live-work complex gives Rue de la Loi a new lease of life

Four lanes of traffic hemmed in by tall office buildings: the current view of Rue de la Loi is hardly the most charming sight in the heart of our capital.
Plans to transform the area have been dragging on for some time, but with the completion of the long-awaited Copernicus project in the European Quarter, the die has finally been cast. The elegant office tower has a subtle appearance and is joined by a stylish apartment building with twelve homes and a roof garden. Thanks to Copernicus’s limited footprint, a green esplanade can also be created, finally giving Brussels’s busiest boulevard some room to breathe.
The transformation of Rue de la Loi is a project that has been on the table for a long time. The first plans by French architect Christian de Portzamparc (‘Stadsproject Wet’) date back more than ten years. The redesign of Schuman Roundabout was a cautious first step, but it took the Copernicus project to get things properly moving. Two outdated office buildings in the European Quarter have made way for a 14,534 m² development: a main building with flexible, modular office space, an adjoining apartment building with twelve spacious homes, and a private underground car park with 69 spaces.

By providing not only workplaces but also 1,386 m² of living space and 1,000 m² of greenery, in the form of a peaceful courtyard garden and a roof garden with panoramic views, this ‘BREEAM Excellent, Core&Shell project’ aims to break up the oppressive ‘canyon of office buildings’ on Rue de la Loi. As the 55-metre-high office tower is set back from the street, the adjoining pavement can also be substantially widened and a green square created. “Copernicus will be the driving force behind the urban renewal of Brussels’s business district. Mature trees and benches will transform the streetscape,” says developer Alides Properties.
A graceful façade
LD2 Architecture was responsible for the design of Copernicus. Algemene Bouw Maes, part of Groep Van Roey, acted as main contractor. “The basement car park was built using in-situ concrete. The office tower’s fifteen above-ground floors are arranged around in-situ concrete cores and consist mainly of a frame of double-height precast concrete columns, beams and prestressed floor units. The apartment block, which has seven above-ground floors, adjoins the office tower and is built from calcium silicate masonry, predalles and in-situ concrete stair cores,” says Thomas Kowalczyk, technical director at Algemene Bouw Maes.
The most striking feature of the finish is the office tower’s imposing façade. The aluminium window frames are largely screened by a white aluminium secondary structure. The subtle interplay of straight and diagonal elements creates a dynamic, gently undulating effect that accentuates the office building’s soaring silhouette. The external structure also ensures the privacy of occupants without compromising interior transparency or the overwhelming sense of space. “It looks complex, but in practice the secondary structure arrived as pre-assembled frame elements, which we simply had to hang in the right place. The ground-floor curtain wall is vandal-resistant and burglar-resistant,” says Kowalczyk.

A logistical puzzle
The main construction challenge lay below ground level. Removing the existing basement and building the new underground car park presented a great many challenges, both literally and figuratively, says Thomas Kowalczyk. “On the one hand, the complex earth-retention work required to create the excavation involved a combination of a secant pile wall and underpinning of existing party walls. Ground anchors could not be used, and part of the secant pile wall had to be propped inwards, using struts and temporary pits that we had to work around. In addition, 230 displacement piles were drilled, and we had to position two tower cranes in the excavation, one of them on a special cast-in anchor.”
“On the other hand, the site’s location, right in the busy centre of Brussels, made for a logistical puzzle. You cannot simply unload a lorry on Rue de la Loi whenever you like, so deliveries of the necessary building materials had to be carefully scheduled. And as every centimetre of space on site had to be put to use, it also took some ingenuity to store all those materials temporarily and sort construction waste in line with BREEAM guidelines. Among other things, we dealt with the latter by arranging daily collections of small containers. Despite the logistical and construction challenges, and a few delivery problems caused by the coronavirus crisis, we are perfectly on schedule to complete the Copernicus project by the end of June 2021!”
Hegge: Glass outer skin
The glass outer skin of the Copernicus office tower is a technical tour de force, in every sense of the word. Façade specialist Hegge (Hamont-Achel) was more than up to the task. “Space on site was very limited, so there was no room for scaffolding or mast climbers. That is why we opted for a unitised façade with prefabricated window frames. The frames were fitted on site with a second, decorative frame, giving the units a length of 4.6 metres, more than 1 metre taller than the storey height. Installing them from the inside was quite a feat,” explains technical-commercial director Andy Coninx. “In total, there were around 1,200 units, which we made to measure in our workshop using Reynaers CW 65-EF profiles, including glazing and all accessories. As the site is in the busy centre of Brussels, transport and deliveries had to be scheduled meticulously, requiring a great deal of coordination and consultation with main contractor Algemene Bouw Maes. Fortunately, everything generally went smoothly and the collaboration was excellent. We were not working as a construction team, but it felt that way, because our expertise was genuinely appreciated. Copernicus is a project we can be proud to list as a reference, especially as unitised façades by Belgian manufacturers are fairly rare in this country.”
Megaton / Structo Prefab Systems: Prestressed concrete floor units
Megaton / Structo Prefab Systems (Ninove) supplies precast concrete products to third parties in Belgium, Luxembourg, the Netherlands and France. As an independent specialist with its own design office, it offers complete solutions using products from the eleven modern production facilities of the Willy Naessens Groep (Megaton, Structo, Intershipping, Interton, Concreton, Alpreco, Altaan, Seveton, Tripan and Willy Naessens Construct), and acts as a point of contact and knowledge centre for these companies. For Copernicus, Megaton / Structo Prefab Systems supplied WX 150, WX 200, WX 265 and WX 500 prestressed concrete floor units. The total area was 9,500 m², spread over fourteen floors and delivered to a tight schedule of one floor every two weeks. The site’s location in the centre of Brussels certainly made things more challenging. Megaton / Structo Prefab Systems is also currently working on several other impressive projects for Algemene Bouw Maes and Groep Van Roey: The Loop Banimmo in Sint-Denijs-Westrem, City Campus in Anderlecht, PPS Centrumontwikkeling in Wezembeek-Oppem, and the new sports and cultural centre in Koningslo.
PROJECT SPECIFICATIONS
Client
Alides Properties (Ghent)
Architect
LD2 Architecture (Watermael-Boitsfort)
Main contractor(s)
Algemene Bouw Maes (Ghent)
Question about this story? Ask your question
Who worked on it
Copernicus in Brussel
- clientAlides Properties
- ArchitectLD2 Architecture
- main contractorAlgemene Bouw Maes
- façade specialistHegge
- gewelven in spanbetonMegaton / Structo Prefab Systems
Keep following this
Get an email when a new story is published. No account needed.
- ProjectCopernicus
- SubjectConstruction projects
- CompanyAlides Properties
- CompanyLD2 Architecture
- CompanyAlgemene Bouw Maes
- CompanyHegge
- CompanyMegaton / Structo Prefab Systems