The finishing touches were recently put to Heidebloem’s new site in Industriezone Europapark in Lanaken.

The look of the new building, which houses offices and a bus depot, is inspired by the bus company’s logo. Green, white and black therefore play an important role in the design, which also has a clear focus on sustainability.

The building comprises 900 m² of office space and 2000 m² of workshop and storage space.

Heidebloem’s new site, a subsidiary of Hansea, was originally planned for a location 200 metres further on, but a few badgers, believe it or not, had other ideas. “I was on holiday when I received a call with an urgent message: withdraw the planning permit for a building on our recently acquired industrial plot immediately if I wanted to avoid a legal battle,” begins Philippe Samyn, general manager of the bus company in Lanaken. “It turned out that there was a badger sett under the plot in question, and these animals are protected by law. Fortunately, with the help of the local authority, we soon found a new location: an adjacent plot in Europark industrial zone, which was also 1 hectare larger at 3 hectares.”

Clear set of requirements

Heidebloem had clear requirements for its brand-new home. “With our new site, which we recently began using, we want to be ready for the future,” says Samyn. “The new site, comprising 900 m² of office space and 2000 m² of workshop and storage space, is therefore focused on the most energy-saving measures and state-of-the-art technologies, including rainwater harvesting, solar panels and LED lighting. A high-voltage substation has also been installed, with cabling to the bus depot. We do not want to wait for politicians before embracing the electrification of public transport. We recently purchased the Hansea group’s first electric bus, for example. Finally, the entire site has been designed to allow for expansion and the possible introduction of new drive technologies for our buses.”

For Heidebloem, it was also important from a corporate branding perspective that the design of its coach fleet should be reflected in the new site. “That is why green, black and white play an important role in the design.”

The office flooring features an inlay that references road markings.

Practical, easy-to-maintain building

“We carefully considered the requirements and designed a practical, easy-to-maintain building. Functional design choices were always weighed against aesthetic considerations,” say Rob Gijsenberg and Kurt Gooris, directors of Buro B architectuur + interieurdesign. “We aimed for an energy-efficient, super-insulated building envelope with a high degree of compactness. In terms of materials, we mainly opted for steel, fair-faced concrete and sandwich panels: honest, durable materials.”

“Thanks to the natural light and open layout, the offices look and feel very airy,” the architects continue. “From the offices, the administrative staff have a good view of the buses coming and going in the depot, which helps to bridge the gap between bus drivers and technicians. We designed the interior finishes with a nod to the sector in which Heidebloem operates. The office flooring, for example, features an inlay that references road markings. The lighting, meanwhile, follows the rhythm of a dashed line on the road. As specifically requested, the colour of the walls and furniture is inspired by Heidebloem’s corporate identity and the look of its coaches.”    

The new site is built mainly from steel, fair-faced concrete and sandwich panels: honest, durable materials.

Challenges during construction

Alongside the preliminary process involving the stubborn badgers, the construction work itself also presented a few challenges. Getting the utility connections in place was not easy, and a wind turbine right next to the site had to be dismantled during construction. A very wet spring also made the tree clearance and earthworks in March more difficult. And then, of course, there was Covid. “When the pandemic broke out, we were faced with a situation we had never encountered before,” says Raf Weytjens, co-director of Herwey, which carried out the earthworks, drainage and infrastructure works. “We quickly implemented the preventive measures imposed by the authorities, so fortunately work on site never stopped. We are particularly grateful to our staff for adopting the measures so quickly and without complaint. Ultimately, deliveries of building materials also continued smoothly. By making the right choices, we avoided delays in that respect too.”

External works first

Following the tree clearance and earthworks, which involved moving 14,886 m³ of soil, the external works were carried out first. “The bus lanes and parking areas are asphalt, while the fuelling areas are made of impermeable concrete,” says Weytjens. “The vehicle parking areas and bicycle shelters, meanwhile, were laid using permeable materials. Considerable investment was also made in underground systems for lighting, data communications and vehicle recognition. The building was then constructed fully in accordance with the proposed BIM model.” Covid was not the only thing that made this project special for Herwey. “Back in 2004, we built an additional car park for Heidebloem’s coaches on the current site. It is great to have been able to roll up our sleeves for Heidebloem and Hansea once again. We are very grateful to them.”

“With our new site and forward-looking technologies, we are underlining our environmentally conscious approach,” concludes Philippe Samyn. “Our site is not only a pleasant place to work for our staff, we can also welcome our customers in comfort and showcase our fleet in ideal conditions.”    

Keysers Noël NV: Fuel installations

Heidebloem’s new site was, of course, also equipped with a filling station. This was handled by Noël Keysers and his eponymous company, which provides complete fuel installation services. “For this project, we installed an underground 80,000-litre diesel tank and a 10,000-litre AdBlue tank,” says his son Olivier Keyers, who is also involved in the business. “We also built a fuelling area and installed the necessary fuel pumps. Our own staff carried out every stage of the installation, using our own equipment and under the supervision of one person in charge. We also take care of the installation’s maintenance ourselves. We consider that important. As we do not depend on third parties, we can always respond quickly. That is why we are available 24/7.”

Keysers Noël NV, whose customers mainly include logistics companies, bus and transport operators, small airfields and heliports, looks back on the project with great satisfaction. “On a new-build project like this, you always have to deal with various parties, including the owner, client, architect, main contractor, roadworks contractor, electrician and IT team. But working with each of them went particularly smoothly,” concludes Olivier Keyers.

TECHNICAL DETAILS

Client 
Hansea (Antwerpen)

Architect 
Buro B architectuur + interieurdesign (Genk)

Earthworks, drainage and infrastructure contractor
Herwey (Lanaken)

Question about this story? Ask your question

Wie aan Vestiging Heidebloem werkte

  1. architectBuro B architectuur + interieurdesignMentioned in Corporate identity helps shape design of new Heidebloem depot
  2. contractorHerweyMentioned in Corporate identity helps shape design of new Heidebloem depot
  3. clientHeidebloemMentioned in Corporate identity helps shape design of new Heidebloem depot
  4. clientHanseaMentioned in Corporate identity helps shape design of new Heidebloem depot
  5. tankinstallatiesKeysers Noël NVMentioned in Corporate identity helps shape design of new Heidebloem depot

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectVestiging Heidebloem
  • SubjectConstruction projects
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.