Asbestos removal at iconic De Brouckèretoren

The former Philips Tower on Brussels’ De Brouckèreplein is undergoing a major refurbishment. Owner Whitewood is stripping the pitch-black building and transforming it into a gleaming white landmark in the capital. This requires extensive asbestos removal work.

De Brouckèretoren Brussel

The remediation zone has been made airtight with plastic sheeting. A three-stage airlock, comprising a ‘clean room’, a shower, a ‘dirty room’ and a wooden materials airlock, allows workers to enter and leave the area safely. The air is regularly monitored inside and outside the enclosure.

The office tower dates from the 1960s and formed part of Paul Vanden Boeynants’ celebrated Manhattan Plan. At the end of 2015, property developers DW Partners, LP and Whitewood bought the 63-metre-high building. Together with CONIX RBDM Architects, they mapped out a new future for the iconic De Brouckèretoren. Whitewood is not demolishing the building, but carrying out a major refurbishment. After De Meuter’s demolition work, only the structural frame will remain, after which contractor Cordeel will reclad the structure. Since November 2018, Renotec has been removing all the remaining asbestos identified in the building’s survey.

Asbestos-safe tower

“Some of the asbestos was removed from De Brouckèretoren during earlier refurbishments,” says Dirk Vandekerkhof, Director of Asbestos Removal at Renotec. “At the time, however, only the asbestos in the way of the refurbishment work was removed. We are now dealing with the asbestos that remains, so that next year we can declare the tower ‘asbestos-safe’. ‘Asbestos-safe’ does not guarantee that no asbestos remains at all, but under normal use, nobody will be at risk of exposure to asbestos.”

De Brouckèretoren Brussel

Asbestos removal workers on site.

Over the past few months, consultancy Kiwa Oesterbaai and Renotec have reviewed the building’s asbestos history and taken samples of materials suspected of containing asbestos, in order to identify all locations where asbestos is present. “The survey was certainly not superficial. We carried out various destructive tests, including cutting holes in the concrete structural columns and examining different floor layers to find hidden asbestos,” explains Vandekerkhof.

A considerable amount of asbestos was found in the building. This is no surprise, as the minerals were popular for many years as fire protection, soundproofing and insulation, and were valued for their reinforcing properties and wear resistance. However, because of the health risks associated with asbestos, it must be removed. The curtain wall of the former Philips Tower will therefore be taken down with due care, as asbestos-containing adhesive was used to attach the cork insulation to the façade elements. Asbestos fibres were also found in various floor finish layers. Renotec must also remove fire-resistant insulation strips from the underside of the structural frame and asbestos-cement service penetrations in the ceiling, as well as fire-retardant door frames and fire barriers in the service risers. 

Hermetically sealed remediation zones

Kiwa Oesterbaai drew up the asbestos survey in spring 2018. The environmental permit is now in place, and De Meuter is carrying out the pre-demolition work. Renotec will get to work once the demolition contractor has finished. “We have divided the remediation operation into six phases,” says Vandekerkhof. “But first we prepared the site. We converted one of the emergency staircases into a ventilation shaft and installed an extraction system on the roof of the third floor. This ‘extractor’ filters the air and maintains negative pressure in the remediation zones.”

De Brouckèretoren Brussel

An external view of a remediation zone set up by Renotec workers. The extraction system on the left filters the air and maintains negative pressure. The area itself has been made airtight.

Renotec is working its way down through the building, from the top to the underground car parks. Containers are used to transport the asbestos-containing materials to Rematt for conditioning before they are taken to a hazardous waste landfill.

A discreet asbestos removal contractor

Renotec is no newcomer to the asbestos removal sector, but it does not make a big thing of it. “That’s right,” says the Director of Asbestos Removal. “We work discreetly. Asbestos is a very sensitive subject. A wrapped building can quickly cause concern among local residents. That is why we always work as unobtrusively as possible.”

Renotec has been carrying out asbestos removal work since 1985 and now has its own team of more than fifty asbestos removal workers. They carry out the work meticulously and are fully protected, so there is no need for subcontractors. The company is also licensed to transport asbestos throughout Belgium. In addition to De Brouckèretoren, Renotec has previously removed asbestos from the nearby Manhattan Tower, the Financiëntoren and the RAC complex, the Flagey building, Antwerp’s Boerentoren, UZ in Ghent, De Warande in Turnhout and the Balmatt site in Mol.  

Remove high-risk asbestos by 2040

The Flemish Government has drawn up an asbestos phase-out plan. All high-risk asbestos must be removed by 2040 at the latest. The highest-risk materials must be removed by 2034. These include asbestos-cement roofing and façade materials, chimneys and easily accessible non-bonded asbestos-containing materials. In time, all buildings dating from before 2001 will also have to have an asbestos survey. The government has pledged to lead by example.

Question about this story? Ask your question

Who worked on it

De Brouckèretoren in Brussel

  1. ownerWhitewood
  2. property developersDW Partners, LP
  3. architectCONIX RBDM Architects
  4. contractorCordeel
  5. demolition worksDe Meuter
  6. asbestos removalRenotec
  7. engineering consultancyKiwa Oesterbaai
  8. clientInterparking
  9. clientImmobel Group
  10. architectCONIX RDBM Architects
  11. main contractorCordeel Group

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectDe Brouckèretoren
  • SubjectConstruction projects
  • CompanyWhitewood
  • CompanyDW Partners, LP
  • CompanyCONIX RBDM Architects
  • CompanyCordeel
  • CompanyDe Meuter
Share this article

Advertisement

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.