Effective drainage on the roof terrace of a new office building

Voor de afwatering van de verschillende terrassen zijn er Profiline-afvoerkanalen geplaatst, die een totale lengte van 110 meter bestrijken.
Voor de afwatering van de verschillende terrassen zijn er Profiline-afvoerkanalen geplaatst, die een totale lengte van 110 meter bestrijken.

In the heart of Brussels’ Sablon district, close to Egmont Park, Tweed immediately catches the eye. This passive, modular, light-filled and sustainable office building has twelve floors and replaces the former building of the Compagnie Intercommunale Bruxelloise des Eaux. The spacious 260-square-metre terrace offers unique, breathtaking views of the city. The efficient linear drainage system is discreetly integrated and comfortably meets current standards. 

“From the outset of the Tweed project, commissioned by Macan Development and AG Real Estate, the building was positioned at the upper end of the Brussels property market,” says Marek Kisielewicz, architect and managing director at ALTIPLAN° architects. “Its position in the city, opposite the Palace of Justice, gives Tweed a distinct identity, which the architecture emphasises through clean lines. It also strengthens the connection with the surrounding buildings, in particular by continuing their existing massing and materiality.” 

“The Profiline channels deliver the required technical performance and fully meet current standards,” says Marek Kisielewicz.

Building with a spacious roof terrace

Tweed’s front façade has a restrained design based on a grid of natural stone. The metal external joinery and glazing combine a classic and contemporary approach. The building’s two upper floors are set back to emphasise the cornice line and align it with those of the two neighbouring buildings. The vertical circulation leads up to the roof, which serves as a spacious terrace. It is easily accessible thanks to technical details that ensure a flush transition between inside and out. “This is possible thanks to ACO’s Profiline channels, which deliver the required technical performance and fully meet current standards,” says Kisielewicz. 

The Profiline channels direct water straight onto the roof waterproofing. The channel is level with the terrace tiles.

The importance of effective drainage

Profiline drainage channels, covering a total length of 110 metres, were installed to drain the various terraces. Jeroen De Vlaminck, Project Manager at main contractor BAM Interbuild, had known ACO for some time, but this was his first time working with Profiline. Both delivery and installation went extremely smoothly. “Naturally, we read the installation instructions first, but the system was easy to install thanks to its user-friendly design and the additional advice from ACO. The subcontractor placed paving supports beneath the channel to ensure perfect alignment,” says De Vlaminck.

The channel, positioned against the façade, will also catch wind-driven rain, prevent water ingress and ensure a smooth flow into the underlying drainage layer,” says Dries Aerts.

The drainage system is integrated into a ceramic terrace floor laid on paving supports, which had to provide a flush threshold. The Profiline channels direct water straight onto the roof waterproofing. The channel is level with the terrace tiles. Dries Aerts, Product Manager at ACO, describes the end result as a combination of aesthetics and functionality. “The channel, positioned against the façade, will also catch wind-driven rain, prevent water ingress and ensure a smooth flow into the underlying drainage layer.” 

The drainage system is integrated into a ceramic terrace floor laid on paving supports, which had to provide a flush threshold.

Meltwater and wind-driven rain too

The Profiline system also complies with Technical Information Sheet 244 issued by WTCB. “In Belgium, this WTCB guidance is unfortunately ignored all too often for terraces on paving supports or timber decking,” says Aerts. “These are usually installed with open joints, allowing rain and snow to penetrate, which makes a drainage channel seem unnecessary.” In such cases, no account is taken of snow accumulating against the façade or wind-driven rain, says the Product Manager. “With Profiline, which complies with TV244, you can drain all meltwater and wind-driven rain quickly and easily. What is more, this is the only way to lower the threshold.” Aerts is therefore very pleased that the architect has been won over by the system: “A good drainage channel is crucial for terraces like these.”    

Een zakelijke vraag aan ACO? Get in touch

Wie aan Tweed werkte

  1. ClientImmobilière de la Laine nvMentioned in A clever blend of classic and contemporary
  2. ArchitectALTIPLAN°architectsMentioned in A clever blend of classic and contemporary
  3. Main contractor(s)BAM InterbuildMentioned in A clever blend of classic and contemporary
  4. Profiline-kanalenACOIn this story
  5. draaideuren en toegangspoortenBoon EdamMentioned in Revolving doors and entrance gates for Tweed office complex

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectTweed
  • SubjectConstruction projects
  • CompanyACO
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.