In the future, low- and intermediate-level category A nuclear waste will be disposed of using highly sophisticated methods. To this end, NIRAS is investing in the so-called cAt project, which includes a brand-new ‘caisson factory’ in Dessel. Delivering this exceptional project required the combined expertise of the very best. The result is a unique building that guarantees the high-quality production of around a thousand caissons a year.

The height was determined by the many overhead travelling cranes and semi-gantry cranes.

Category A waste is processed and conditioned waste containing a small quantity of radioactive substances. It is therefore suitable for near-surface disposal, a long-term solution in which the waste is passively contained so that it will not harm people or the environment. Specifically, it is placed in concrete boxes (caissons) and then encapsulated in mortar to form monoliths. These are placed in modules: concrete bunkers with thick reinforced-concrete walls, sealed with a concrete cover slab. These in turn are given a permanent final cover that is virtually impermeable to water. 

Part of the building houses large hoppers for aggregates.

Large-scale factory 

This process is part of the cAt project, which NIRAS (Belgian Agency for Radioactive Waste and Enriched Fissile Materials) has been developing since 2006. The aim was to combine a technically safe solution for category A waste with a social and economic project plan. Dessel was ultimately selected as the site. From 2022, part of this process will take place in the new ‘caisson factory’ on Europalaan. “Given the high and specific quality requirements, all the concrete is produced on site,” says Dennis van Put, project manager for TM Vanhout-Stadsbader. “It has therefore become a fairly large production facility, with its own concrete batching plant and a hall where the reinforcement cages are prefabricated. The factory also has a fully equipped concrete laboratory. In addition, there is a production hall where the caissons are made and a conditioning hall where they can cure under ideal conditions. Finally, there is also a concrete recycling hall.”

The factory was finished with a grey concrete plinth and internal liner panels with dark-coloured cladding.

Simple choice of materials

The factory covers an area of 2,800 m² and is 12 metres high. “The height was determined by the many overhead travelling cranes and semi-gantry cranes, which ensure the smooth internal transport of materials, caissons and their covers,” explains Dennis van Put. “Three storage bunkers for aggregates were also provided outside. Finally, an adjoining two-storey office complex with an area of 770 m² was built. It has a concrete frame and load-bearing concrete blocks. This is a fairly simple volume, finished with grey sandwich-panel cladding. The factory is designed as a steel frame on concrete plinths. For the finishes, a grey concrete plinth and internal liner panels with dark-coloured cladding were chosen, matching the other projects on the site.”    

The unloading bays are strategically positioned.

An engineering marvel

It goes without saying that TM Vanhout-Stadsbader had to take a great many requirements into account. “For example, the building has to withstand earthquakes, which is not an everyday requirement in Belgium,” says Dennis van Put. “It was an exceptionally complex assignment, especially in terms of structural stability and building services. The production processes are highly automated, for instance, and the factory will be partly powered by geothermal energy. NIRAS therefore awarded the project on a Design & Build basis, and we decided to form a Temporary Joint Venture. Vanhout and Stadsbader were responsible for the building and building services, as well as the entire infrastructure. We also coordinated the subcontractors and the other participants in the joint venture. These included Grimbergen, which was responsible for the complete operational installation used to make the caissons, and Smet Tunneling, which handled the geothermal installation. Together, we demonstrated a strong capacity for innovation. The ‘caisson factory’ is, after all, an engineering marvel that we can all be proud of.”  

Facilities were provided to bring raw materials into the factory efficiently.

Een zakelijke vraag aan Stadsbader? Get in touch

Who worked on it

Caissonfabriek NIRAS Dessel in Dessel

  1. main contractorStadsbader
  2. ClientNIRAS
  3. ArchitectA Cube Architecture
  4. main contractorTM Vanhout
  5. operationele installatieGrimbergen
  6. geothermische installatieSmet Tunneling
  7. HVAC systemBelcotec

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectCaissonfabriek NIRAS Dessel
  • SubjectConstruction projects
  • CompanyStadsbader
  • CompanyNIRAS
  • CompanyA Cube Architecture
  • CompanyTM Vanhout
  • CompanyGrimbergen
Share this article

Advertisement

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.