Euroports warehouse, Kallo | Bright blue port warehouse built in record time

Euroports warehouse, Kallo | Bright blue port warehouse built in record time

A total floor area of 17,372 square metres, a length of 202 metres, a width of 86 metres and a height of 17 metres: the figures behind the new Euroports warehouse in Kallo, one of the largest in the Port of Antwerp, speak for themselves. Especially when you consider that it was fully wind- and watertight in just four months. The bright blue warehouse is leased by Zimmer Staal and was designed and built to meet the renowned steel producer’s requirements by ASK Romein.

lucid_ask_euroports_04-kopieren

The bright blue sandwich panels ensure that the building
really stands out.

Euroports is an international terminal operator with four terminals in the Port of Antwerp. At the Vrasenedok on the Left Bank, it had a substantial warehouse built, which was recently taken into use by Lier-based company Zimmer Staal. All kinds of steel components from far-flung places such as India and China, amounting to 120,000 tonnes a year, can be stored there before being shipped to other European countries. The new warehouse represents an investment of around 20 million euros and fits perfectly with the ambition to further boost steel traffic in the Port of Antwerp.

lucid_ask_euroports_13-kopieren

Two large built-up lattice trusses each span 41 metres, while four lattice columns have been installed across the full width of the warehouse.

1,030 tonnes of steel

The new warehouse is one of the largest in the Port of Antwerp. “It consists of an imposing steel structure, made wind- and watertight with steel decking, concrete plinths and bright blue sandwich panels, which ensure that the building really stands out,” says Tom Vroon, project manager at contractor ASK Romein. “Two large built-up lattice trusses each span 41 metres, while four lattice columns have been installed across the full width of the warehouse, two in each half. No less than 1,030 tonnes of S355 steel have been incorporated into the structure.” ASK Romein built the warehouse for Euroports, but tailored it entirely to the needs of tenant Zimmer Staal. A rooflight integrated into the flat roof provides abundant natural light, helping to reduce electricity costs for artificial lighting. A 2.54-metre-wide access platform runs the full length of the warehouse. Zimmer Staal has not only a shot-blasting machine for cutting steel plates, but also a paint line and four high-capacity overhead cranes that can lift steel components weighing up to 20 tonnes, hence the height of the building.

lucid_ask_euroports_16-kopieren

Four high-capacity overhead cranes can lift steel components weighing up to 20 tonnes. Hence the height of the building.

A very tight deadline

ASK Romein looks back on a highly successful project. “At ASK Romein, we have specialised in building large industrial warehouses for many years,” says Tom Vroon, “so from a technical point of view, this was not an unusual project for us. However, the deadline was extremely tight. The warehouse had to be fully wind- and watertight within four months. It was a race against time, and we won it with flying colours! Euroports is extremely satisfied.”    

Question about this story? Ask your question

Who worked on it

Euroports-loods in Beveren-Kruibeke-Zwijndrecht

  1. contractorASK Romein

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectEuroports-loods
  • SubjectConstruction projects
  • CompanyASK Romein
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.