Expert façade renovation for a beleaguered Amelinckx block

When you enter Sint-Niklaas via the E17, you can’t miss them: five large apartment blocks, each with sixteen storeys and around 200 flats.
The ‘Amelinckx blocks’ date from the late 1960s and are a landmark in the region. Over the past few months, renovation and restoration specialist IBT nv from Wetteren has given Residentie Fabiola 3 a new look, on behalf of property manager Immo Van De Woestijne and under the expert supervision of Bureau voor Expertise en Architectuur.
When the Amelinckx blocks were built, the ambitious project carried considerable prestige. High-rise buildings in a provincial town such as Sint-Niklaas captured the imagination, especially as the thousand flats are set in a green parkland setting. It was modern urban development avant la lettre, although the ravages of time are now taking their toll. “As is often the case with buildings of this kind, all structural maintenance work has been postponed in the past, and suddenly a great deal needs to be done at once to maintain the quality of living,” says Karen Van De Woestijne, managing director of Immo Van De Woestijne. “Together with Joost Beke from Bureau voor Expertise en Architectuur, we drew up a master plan to renovate Residentie Fabiola 3 in phases. The refurbishment of the west façade has just been completed. Next comes the underground level, and finally, in 2024, we will tackle the east façade.”

Leaching and frost damage
The structural renovation of Residentie Fabiola 3 could not come soon enough, as the building was in poor condition. “The problem with apartment blocks of this kind is that they generally have no waterproofing, leading to aesthetic deterioration and technical problems such as leaching of the concrete,” explains Joost Beke. “The same was true of Fabiola 3. The entire terrace structure was dismantled down to the bare concrete, where we also found frost damage. A substantial amount of concrete repair work therefore had to be carried out before the new floor build-up could be installed. Fortunately, we had a skilled contractor with the necessary experience in projects of this kind. All the terraces have been refurbished, giving residents extra space thanks to the balustrades being fixed at the ends.”
A solutions-focused approach
“IBT nv from Wetteren did an excellent job here, which was no mean feat during the pandemic,” stresses Karen Van De Woestijne. “The demolition work had just been completed and reconstruction was about to begin when the ‘lockdown’ was announced, so a great deal of adaptability was required. Another advantage was that IBT nv took a very solutions-focused approach and contributed ideas proactively. They don’t simply follow instructions blindly, but put all their construction expertise to work to create real added value. At Fabiola 3, this meant optimising the balustrades, fixings, downpipes, concealed terrace drainage and floor build-up … Much to the residents’ delight, they are thrilled with the end result!”
Question about this story? Ask your question
Who worked on it
Residentie Fabiola 3 in Sint-Niklaas, renovatie
- syndicusImmo Van De Woestijne
- renovatie- en restauratiespecialistIBT nv
Keep following this
Get an email when a new story is published. No account needed.
- ProjectResidentie Fabiola 3
- SubjectConstruction projects
- CompanyImmo Van De Woestijne
- CompanyIBT nv