Functional new-build reflects an ambitious long-term vision

Last summer was a time for celebration at Breetec: on 15 July 2021, the company turned 40. As befits an ambitious business, the anniversary was marked in style. Owners Koen and Sandra Beckers treated themselves and their staff to a 1,000 m² new-build, increasing capacity by 30 to 40%. Another notable feature is that this highly functional building was constructed entirely to BEN standards.

A takeover, the opening of an overseas branch in the Czech Republic, a major change in personnel … Breetec has faced no shortage of challenges in recent years. On top of that, the rapid spread of coronavirus led to a ‘lockdown’ in our country on 18 March 2020. Yet on that very day, the specialist metal construction company from As signed the contract for an impressive new building with additional production and storage space, representing an investment of 1.2 million euros. It was a bold move, although the company’s management had certainly not taken the decision lightly. The first seeds of this ambitious expansion project were sown back in 2013, when the land next to the existing site was purchased. Cancelling was therefore not an option, especially as rising demand in export markets called for a substantial increase in capacity. The newly completed building secures Breetec’s future and continued organic growth.

Carefully planned circulation
Despite the unwelcome effects of the coronavirus crisis, construction of the new Breetec building took just nine months. The detached building covers an area of 1,000 m² and is situated next to the company’s existing
buildings. A gate at the rear connects the two production units. “The general administration is still based in the existing section, while all the office and reception areas in the new building are related to production,” explains Rob Gijsenberg, architect and managing director at BURO B architectuur + interieurdesign.

“One of the key considerations during the design phase was ensuring easy access, particularly as large articulated lorries needed to be able to drive into the warehouse, where sizeable components can be loaded and unloaded using an overhead crane. With industrial construction projects like this, we always start by planning the circulation carefully so that we can optimise movement around the site. We have provided direct access from the street,
including an airlock for night-time deliveries and a covered entrance for drivers and other staff. There is also a separate entrance for customers and suppliers who do not need to enter the warehouse. The ground floor also accommodates toilets, changing rooms and a kitchenette. The offices are located on the first floor.”

Meets BEN standards
Although functionality was the priority for the new building, Breetec set the bar high, particularly in terms of sustainability. “The building is insulated to BEN standards, and solar panels, a heat pump and a heat-recovery ventilation system keep the use of fossil fuels to an absolute minimum. White roof covering was also chosen to prevent the warehouse and associated offices from overheating. This reduces the cooling load and, in turn, cuts energy consumption further,” explains Rob Gijsenberg.
As the building is a compact, two-storey volume, its spatial footprint was also kept within bounds. “When landscaping the site, we also aimed to make optimum use of the land and ensure sustainability, including by installing a large underground infiltration basin,” Gijsenberg emphasises. “The materials chosen include a steel frame and a combination of fair-faced industrial concrete and black sandwich panels on the exterior. We enjoy creating beautiful things, but in most of our projects, aesthetics are a welcome by-product of functionality. First, we make sure all the pieces fit together, then we turn them into an attractive whole. That is exactly what we did with Breetec’s new building, which fits in perfectly with the streetscape. The client is clearly delighted, so we can be proud of what we have achieved!”
Question about this story? Ask your question
Who worked on it
Breetec-gebouw in As, nieuwbouw
- clientBreetec
- architectBURO B architectuur + interieurdesign
- main contractorJaraco
Keep following this
Get an email when a new story is published. No account needed.
- ProjectBreetec-gebouw
- SubjectConstruction projects
- CompanyBreetec
- CompanyBURO B architectuur + interieurdesign
- CompanyJaraco