Gazo, Sint-Truiden | Acoustics a major challenge for external joinery contractor

Acoustics were a crucial consideration in the GAZO project. This naturally had a considerable impact on the external joinery. The range of stringent acoustic requirements posed a serious challenge for window and door specialist Ramen Dexters.
“We installed around 2,300 m² of aluminium external joinery in total,” says Marco Dexters, former managing director, who is still active in the company. In recent years, the company has focused exclusively on the project market. “We also installed fire doors, solar shading systems, glass balustrades, solar control glazing and a glass canopy over part of the playground, among other things. Almost all the doors are fitted with special automated motor locks to enable extensive access control.”

The stringent acoustic requirements included the use of double windows with a 30-centimetre cavity between them.
An acoustic tour de force
Following extensive research by a consultancy, around ten different acoustic levels were specified for the GAZO site, depending on the function of each space and its orientation within the project, ranging from 28 dB to approximately 50 dB of sound reduction. “It was important to limit sound transmission between the various spaces, particularly between the reception area and the party room, which are linked by an open void, but also from inside to outside, in the music classrooms, and vice versa, given the proximity of the station and a busy main road. The study resulted in, among other things, steel connections between the windows and the structural shell, supplemented by airtight membranes, as well as double windows with a 30-centimetre cavity containing sound-absorbing insulation and perforated aluminium panels. Almost every window is fitted with special acoustic glass, each with its own specific dB reduction rating. The windows themselves also had to be manufactured with particular care. Obtaining the available certificates, or confirming that none existed, for the various sound levels was also a tour de force. However, thanks to close collaboration with the glass supplier and aluminium suppliers SAPA and WICONA, both part of the Hydro Aluminium global group, this almost insurmountable task was also brought to a successful conclusion,” says Marco Dexters.

The reception hall overlooks the party room through an open void. Sound transmission between the two spaces was absolutely unacceptable.
Getting everyone on the same page
“The huge glass canopy over the primary school playground is another special feature,” adds managing director Koen Dexters. “The 220 m² trapezoidal canopy, with its concealed drainage system, provides a safe haven in wet weather and connects two wings in an architecturally considered way.”
“As well as the huge acoustic requirements, which led to a significant increase in the budget, completing the job in just eight months was no easy task. We are particularly proud of this progressive project. We are also very pleased with our collaboration with the city council, the architectural firm and, above all, Peter Jamin, project manager at Democo, who managed to get all the parties involved on the same page,” concludes Marco Dexters.
A business enquiry for SAPA? Get in touch
Wie aan GAZO werkte
- masterarchitectArchitecten AchtergaelMentioned in Gazo, Sint-Truiden | Multifunctional use of space ensures optimal occupancy
- contractorDemocoMentioned in Gazo, Sint-Truiden | Multifunctional use of space ensures optimal occupancy
- raam- en deurspecialistRamen DextersIn this story
- aluleverancierWICONAIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectGAZO
- SubjectConstruction projects
- CompanySAPA
- CompanyRamen Dexters
- CompanyWICONA