Halle, Residentie Huiskensveld | Stylish assisted living complex completes the picture

Residentie Huiskensveld herbergt veertig gloednieuwe assistentiewoningen van 45 m². Aannemer Antwerpse Bouwwerken was verantwoordelijk voor de uitvoering van dit project.
Residentie Huiskensveld herbergt veertig gloednieuwe assistentiewoningen van 45 m². Aannemer Antwerpse Bouwwerken was verantwoordelijk voor de uitvoering van dit project.

Halle takes good care of its senior citizens. Exactly 25 years after the first ‘service flats’ at Centrum Van Koekenbeek came into use, work got under way just a few metres away on Residentie Huiskensveld.

This elongated new-build complex now houses forty brand-new assisted living apartments measuring 45 m², built above a spacious underground car park. Linked by glazed walkways, the two buildings form a trio with the neighbouring residential care centre Zonnig Huis, which can also look forward to a new dementia garden. 

The external envelope combines curtain walls with thin-joint masonry.

When it opened in 1994, Centrum Van Koekenbeek marked a real milestone in elderly care in Halle. A quarter of a century later, demand for social assisted living apartments still exceeds supply, so Residentie Huiskensveld came at just the right time. The number of residential units on the site doubled overnight, from 41 to 80. The new building is linked by walkways to Centrum Van Koekenbeek and the residential care centre Zonnig Huis, allowing residents to use the same facilities, including activities, a hairdresser, chiropodist and dining room. An underground car park with space for 68 cars was also built. Residentie Huiskenveld, whose name refers to the site’s former name, was designed by the Dutch practice Gortemaker Algra Feenstra. Construction was managed by Lennik-based Licence to Build. 

Stepped massing with roof terraces

Antwerpse Bouw-werken, part of the Eiffage Group, was responsible for the complete package, including the structural work, finishes, building services and landscaping. “We started at the end of February 2019 on a vacant site that still needed some tree clearance,” says site manager Freek Amys. “We then excavated a construction pit of around 2000 m², involving 7000 m³ of earthworks. The construction schedule was fairly tight, so we made maximum use of precast concrete elements at basement level.
The building has four storeys above ground, with the floor area decreasing gradually at each level, from 823 m² on the ground floor to 613 m² on the third floor. This allowed us to create a green roof terrace on every level. The amount of glazing in the central corridor also increases with the building’s height. The central lift core is built from solid precast concrete walls, while the load-bearing walls are made from calcium silicate blocks finished with fine plaster. They are topped by a predalle slab, which transitions into hollow-core slabs at the roof terraces. The ceilings in the central corridors are finished with a special wood-effect finish sourced from Portugal. The external envelope combines curtain walls, including aluminium flashings to conceal the integrated solar shading boxes, thin-joint masonry, windows with powder-coated aluminium frames, two per apartment, and projecting precast terraces with exposed concrete on top, timber cladding underneath and painted steel balustrades clad in anodised aluminium panels. We also carried out the landscaping, installing various types of planting and paving and building 200 lm of retaining walls ranging from 1.5 to 5 metres high. These were made from light-coloured ready-mixed concrete and formed using special large-format formwork panels to achieve a cleaner finish.” 

The central corridors are finished with a special wood-effect finish sourced from Portugal.

Walkways demand precision

The standout architectural features of Residentie Huiskensveld are undoubtedly the glazed walkways connecting the new building to the residential care centre Zonnig Huis and Centrum Van Koekenbeek, an existing assisted living complex. “The design contained almost no detailing, so we had to work out the steel structures ourselves, including the connections and expansion joints. It was no easy task, especially as they range from 15 to 17 metres in length and had to be assembled at fairly short notice,” explains Freek Amys. “The steel structures arrived from the workshop partly pre-assembled. We assembled the top and bottom surfaces and the steel decking on site. We then lifted the walkways, which rest on columns and anchors, into position as complete units. It was a nerve-racking operation, but everything fitted perfectly. Finally, we fitted curtain wall systems with integrated solar shading on both sides and insulated the roofs. Another notable feature is that the walkways have underfloor heating, just like the building itself, despite their thin floor build-up.”

The projecting precast terraces have painted steel balustrades clad in anodised aluminium panels.

Limited impact from COVID

Residentie Huiskensveld was completed on 10 December 2020. “Looking back, the work went very well, although COVID did throw a spanner in the works,” says Freek Amys. “We initially had everything well organised, partly thanks to our excellent lean planning, but during lockdown we had to temporarily stop work on site. We then resumed work gradually, although the measures in place meant we could not work at the same pace as before. Deliveries also brought their share of difficulties and delays. Getting back into the swing of things was no easy task, but overall we managed to limit the impact. This was not a small project, and we are also building a new dementia garden for the residential care centre Zonnig Huis, on behalf of the OCMW. It will comprise a therapy room on the ground floor and a terrace on the first floor, including two architectural concrete benches, a canopy and a rabbit hutch. The dementia garden will be ready in April 2021.”    

Drafab | Interior finishing

Fitting out the assisted living apartments at Residentie Huiskensveld called for a great deal of bespoke work. Drafab, based in Poperinge, was therefore brought in for the job. With three generations of woodworking expertise and a state-of-the-art machine park, the company was ideally placed to deliver this type of project. “Precise finishing and watertight quality guarantees are what set us apart,” says managing director Dries De Backer. “We were responsible for all the interior finishing in the forty assisted living apartments. Each flat had a largely identical fit-out: a built-in wardrobe in the entrance hall, a fully fitted kitchen and built-in wardrobes in both the bedroom and bathroom. We also handled the finishes in the communal areas, where we installed a large quantity of bespoke fitted furniture and benches. These had to be fitted into alcoves, with timber panelling on both sides. This presented a number of challenges, as the many irregular shapes all had to be cut with mitred joints.”

PROJECT DETAILS

Client Stad Halle
Architect Gortemaker Algra Feenstra (Rotterdam, Netherlands) & Licence to Build (Lennik) 
Main contractor(s) Antwerpse Bouwwerken (Antwerp)

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectConstruction projects
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.