Social housing provider De Brusselse Woning has given its Huidevetters-Wasserij residential complex a thorough makeover. It has also revamped the courtyard shared by this complex and other buildings owned by the housing provider.

The building’s old stairwells have been removed. “They hampered the new layout of the flats and were unnecessary in several places. The flats can now be accessed via two open stairwells. The first is inside the building, while the second is outside,” says architect Gaëlle Cnop. “These new stairwells are beneficial in terms of energy savings. Their open design allows them to be naturally ventilated and lit.”

De Brusselse Woning geeft woonkwaliteit nieuwe dimensie

The rear façade before the works.
(Image: Floré)

More living space

Walkways on the third and newly built fourth floors connect the two stairwells. “Several recesses break up the originally solid building into smaller volumes, allowing more light to enter. This creates cosy intermediate spaces and terraces.”

Originally, the complex contained 32 social housing flats. Despite its larger volume, the renovated building now has just 23. This means tenants have more living space. Every flat now includes a play area for children. They can also let off steam on a circuit around a central ‘box’. This houses all the functional spaces that do not require natural light, such as the bathroom and a storage room. The dual-aspect flats face both the inner courtyard and the street.

View of the street façade.

Pragmatic layout

“In the design and allocation of the various flat types, we took a pragmatic approach, placing similar functions above one another to keep junctions and service risers highly rational. Economic viability and straightforward technical maintenance are priorities for a social housing provider. We also stacked the same flat types vertically to ensure a mix of flat types on every floor.”

The courtyard, formerly used mainly for parking, is now a semi-public green space. It is open to everyone during the day, but is closed in the evening so that only residents can access it. “The only way to bring this square to life was to connect it directly to the building. That is why the former anonymous rear façades have been designed as front façades,” says
architect Gaëlle Cnop.

A group of five planters for medium-height planting in the middle of the park adds a sense of movement and relief. Wooden benches follow the lines of the concrete planters, creating more intimate areas. Tables are intended to encourage social interaction. The planting, private terraces and carefully designed slopes shield the ground-floor flats from the public space.

Unexpected challenges

“The renovation was too extensive to carry out while residents were still living there,” recalls project manager Wouter Vangeel of main contractor Floré. “We also carried out the demolition work, which threw up a few surprises. For example, the old floors turned out to be made of terracotta vaults. These can no longer be used today because of their limited load-bearing capacity. As a result, we had to shore up the entire building first, then reinforce the roof slab and floor slabs from top to bottom, replacing them where necessary.”

The front and rear façades have been completely modernised. They were previously made of brick-
masonry, finished with prefabricated façade panels. The new façade finish, insulated to current standards, consists partly of render and partly of ceramic tiles. Tiles, the most wear-resistant option, have been used mainly on the ground floor and the recessed terraces. The additional floor, on the other hand, is predominantly rendered.”

Floré used aerated concrete for the additional floor and the new internal walls in the existing building. “Because it is a very lightweight material. We also used aerated concrete for the top roof slab, a specialist product from the same manufacturer. It supports an extensive green roof.”

Question about this story? Ask your question

Who worked on it

Huidevetters-Wasserij in Brussel

  1. main contractorFloré

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectHuidevetters-Wasserij
  • SubjectConstruction projects
  • CompanyFloré
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.