Iconic tower becomes ‘Urban Platform’

The celebrated Brouckèretoren in the centre of Brussels is no more. Not in its original form, at least: the modernist office complex has been transformed into a mixed-use building named ‘MULTI’. The result is a new landmark that incorporates sustainability in a unique way. The tower has evolved from a dark, heavy box into a transparent, welcoming ‘Urban Platform’ that acts as a connector between the surrounding neighbourhoods.

The Brouckèretoren helped shape the Brussels cityscape for more than fifty years. Not always in the most positive way, as the building had lost much of its grandeur in recent decades. However, repurposing it as a residential tower was not an obvious choice given its location and the scale of the works. Developers Whitewood and Immobel Group eventually decided to take on the challenge, together with CONIX RDBM Architects and contractor Cordeel Group. “We set the bar very high,” says Frederik Jacobs, CEO-architect at CONIX RDBM Architects. “First and foremost, we wanted to increase the usable floor area by 6,400 m², bringing it to a total of 44,200 m². We also wanted to create a mixed-use building where the horizontal movement of people passing through would reinforce the vertical movement of living and working. Furthermore, our ambition was to develop ‘MULTI’ as an ‘Urban Platform’ and ‘Urban Connector’ that supports and enhances the pedestrian zone. To that end, we made the building as accessible as possible, provided urban terraces and gave the outdoor space a public character.”

Circularity at the heart of the project
The construction team also made a firm commitment to achieving BREAAM Excellent certification, an ambitious target for a renovation project. Naturally, this involved opting for maximum insulation, PV panels and heat-pump heating. “We also focused on circularity,” says Frederik Jacobs. “Together with Rotor Deconstruction, we explored the possibility of using as many reclaimed materials as possible. For example, the original Belgian bluestone was reused in ‘MULTI’, and flooring from ’t Zand in Brugge was also incorporated. We also reclaimed around four hundred Jules Wabbes granite tiles from the Generale Bank for the terrace. In addition, we incorporated approximately 1,300 metres of aluminium profiles from the Brouckèretoren into the balustrades and light fittings in the atrium of the renovated tower. Reuse on this scale is truly unprecedented in Belgium.”

Light and transparent
‘MULTI’ does away with the enclosed feel and dark colours that characterised the original tower. The existing structure therefore had to be completely stripped back, then structurally strengthened using steel beams and columns, bonded reinforcement and extensions to the existing concrete columns. “The building had to be extended in two dimensions,” explains Frederik Goossens, project manager at Cordeel Group. “The floor plates were enlarged, and the building was extended upwards to nineteen above-ground storeys. After the existing plant room was demolished, new precast concrete columns, slabs and beams were installed. A double-height steel storey was built above this additional level, with cellular concrete panels used for the roof. We then installed a completely new façade, made up of aluminium frames spanning the full storey height. The extensive glazing and light-coloured façade create a transparent, welcoming whole. The glazing has a low g-value to showcase the activity inside. Decorative aluminium and Neolith elements add further depth to the façade units. The base was also restored: the bluestone panels were renewed, and new large windows based on the historic design were installed. The result is a dynamic building that seems to absorb its surroundings.”

Practical challenges on site
In addition to coordination, Cordeel Group’s companies were responsible for the concrete and steel structures, timber joinery and building services (HVAC, plumbing and electrical installations). “The rest was subcontracted to competent specialist firms,” says Frederik Goossens. “Although, as one of Belgium’s largest Class 8 contractors, we are used to dealing with complex projects, ‘MULTI’ presented challenges that demanded a great deal of creativity. A site with limited working space in the heart of Brussels requires more than just-in-time deliveries. We also had to ensure that the right quantities of materials were available on the relevant floors at all times. In short, deliveries had to follow a complicated logistical puzzle that only the best planners could solve. It was also unusual to have to carry out work while businesses were still operating on the base levels. We addressed this with temporary seals and screens, good communication and rapid responses to incidents. Finally, incorporating reclaimed materials presented an entirely new challenge.”

A landmark project for all parties
The full renovation took 34 months. The end result, however, is a resounding success. “‘MULTI’ is a highly interesting reference project for Cordeel Group,” says Frederik Goossens. “We are proud to have played our part in repurposing this landmark in the heart of Brussels. Its circular approach also makes the project a perfect fit with our own vision of sustainable construction. Last but not least, it is an excellent showcase of the group’s ability to deliver the entire construction process as a one-stop shop.” Frederik Jacobs adds: “For CONIX RDBM Architects, this iconic project is the ultimate outcome of exemplary collaboration between all the parties willing to commit to circular construction on such a large scale. Mission accomplished.”

Question about this story? Ask your question
Who worked on it
De Brouckèretoren in Brussel
- ownerWhitewood
- property developersDW Partners, LP
- architectCONIX RBDM Architects
- contractorCordeel
- demolition worksDe Meuter
- asbestos removalRenotec
- engineering consultancyKiwa Oesterbaai
- clientInterparking
- clientImmobel Group
- architectCONIX RDBM Architects
- main contractorCordeel Group
Keep following this
Get an email when a new story is published. No account needed.
- ProjectDe Brouckèretoren
- SubjectConstruction projects
- CompanyImmobel Group
- CompanyCONIX RDBM Architects
- CompanyCordeel Group