In the heart of one of Ukkel’s most popular neighbourhoods, the renowned Edith Cavell clinic has made way for a high-end residential development of 19,000 m², with 136 flats and five shops spread across five independent buildings. This large-scale project was characterised, among other things, by demolition works carried out in phases, during which the concrete structure of the central ten-storey tower was retained. The site’s poor accessibility, the complex connection between the existing and new structures, and the wide variety of finishes and systems pushed the contractor to its limits.
Simon Haut, project engineer at CIT Blaton: “Work on this site began in March 2019 with a year of demolition. We then carried out the structural works, block by block, before moving on to the finishing works. The project was completed at the end of last year. The site was in the centre of Ukkel, which meant that we had to use sections of the road for storage. This caused considerable disruption for local residents. They had to be patient, as the work unfortunately ran over schedule, mainly because of the Covid crisis.”
The Edith Cavell clinic made way for a high-end residential development with 136 flats and five shops.
As the demolition work had to be carried out over three underground car park levels, it was no easy task to get the right machinery into the right places. Mountains of rubble had to be cleared, and countless props were needed.
Built around the existing structure
The plan was to demolish and rebuild the four small, four-storey buildings. Block B, the ten-storey tower, had to be brought up to current standards, and a new structure had to be added to achieve the volume envisaged by the architect. Simon Haut: “This was undoubtedly the biggest technical challenge, because the finished floor levels did not match those in the plans. For example, we had to tie the balconies into the existing structure by adjusting the screed and finish levels, not to mention the insulation, as this is a passive building.
The interior finishes are similar in the flats in the smaller buildings, while buyers could choose the finishes for the tower flats.
Fortunately, we could rely on our own in-house design team to carry out the necessary recalculations and determine what needed to be done, and using which construction methods. It is quite unusual in our sector to be able to do this in-house, and it really helped us overcome the challenges.” The in-house design team also had to recalculate the EPB performance to adjust the insulation thickness, so that the balconies would be level with the interiors of the flats.
To deal with these unforeseen complexities, CIT Blaton had to mobilise no fewer than nine project managers and site managers to oversee the day-to-day work. Two teams of construction workers handled the structural work: one worked with subcontractors, while the other comprised CIT Blaton’s own employees, who took care of the most complex elements.
All the flats sold very quickly.
A variety of materials and systems
The façades are distinguished by their wide variety of finishes: natural stone, rendered brick, zinc, balconies and terraces with glass balustrades … The level of detail was high, requiring meticulous coordination. The interior finishes are similar in the flats in the smaller buildings, but not in the tower flats, which buyers could finish to their own specifications. Each future owner could choose their own tiles and joinery. CIT Blaton also carried out the finishing work, delivering an excellent result. The fact that all the flats sold very quickly speaks volumes. With 1,000 m² of shops on the ground floor, two hundred underground parking spaces and a 2,000 m² courtyard garden, there is no doubt that residents will find a new lease of life in a place where patients were once treated.
Block B, the ten-storey tower, had to be brought up to current standards, and a new structure had to be added.