Kortrijk LAGO Kortrijk Weide | Aesthetic durability for Kortrijk’s new swimming complex

Alongside entertainment, sustainability is the key to success for West Flanders’ largest swimming complex. And it was worth paying a premium for. A €30 million construction investment that did not go entirely smoothly, but one that resulted in low maintenance costs and high aesthetic value.
An Olympic pool measuring 50 by 21 metres with spectator seating, a water park with five slides and the Benelux’s longest wild water ride, an all-weather outdoor pool with a sunbathing lawn, three children’s pools with a water playground, a wave pool, a warm lagoon with water massage, two saunas and a steam room. The list of attractions at LAGO Kortrijk Weide is impressive. So too is the fact that the parties involved rose to the many aesthetic and sustainability challenges. As a co-shareholder in the S&R Group, main contractor ACH Bouw is committed to guaranteeing quality in the long term. The lower the building’s running costs, the more can be invested in new attractions. 30 per cent of ACH Bouw’s activities are in the swimming pool sector, so it has plenty of experience. Even so, it encountered a few unusual challenges along the way.

Stainless steel and steel balustrades require little maintenance and withstand a chlorine-rich environment.
Tight deadline
Meeting the deadline was one such challenge. “It started with the location,” says project manager Steven Beyaert. “There used to be a storage depot belonging to NMBS there. The soil was contaminated and had to be remediated.” The entire site underwent extensive work. Building the swimming pool was just the tip of the iceberg. “We could only access the site from one side,” says Beyaert. “Kortrijk city council’s plan to minimise disruption also caused us some stress. We had to take the neighbouring schools and noise pollution into account.”
In the end, everything was completed on time. Then a fire shortly before the opening threw a spanner in the works. The slides were partially destroyed by fire. Thanks to the well-designed concept and compartmentalisation in the
concrete, worse was avoided. Fire-resistant RF doors separate the sports area from the leisure zone. This protected the sports pool, the Rest-eau-café, the changing rooms and the administrative area.

The Benelux’s longest wild water ride is in Kortrijk: 160 metres of non-stop fun. (Image: Fotodesign Emily)
Technical challenges
The construction of the Olympic pool alone was a major technical feat. One half has a fixed floor at a depth of 2 metres, while the other has a movable floor that can also be divided lengthways into sections of 25 and 22 metres. This means one end can be set to a depth of 70 centimetres and the other to 1.40 metres, depending on demand. Because the complex also had to fit into its surroundings at Kortrijk Weide, aesthetics played an important role. “Other buildings are generally designed with structure as the priority, so there is less cost involved in that respect,” explains Beyaert. “By combining brick slips, black render and glass façades, we achieved a sleeker, more attractive overall look, but at a higher cost.”

The window frames are made from special alloys for use in swimming pools.
Sustainability is a winning feature
Sustainability is evident throughout the building, from the latest PV technologies and combined heat and power to extra-insulated roofs and triple thermal glazing. The timber roof structure is clad with wood wool cement boards, an ideal choice for acoustics, aesthetics and moisture management. The external joinery is also designed for a chlorine-rich environment. The glass façades have been installed in reverse, with the profiles on the outside. They are made from special alloys for swimming pool applications.
Buffer tanks beneath the building help make the water park energy-efficient. Every evening, the water from the main pool is stored in the tanks. The other pools are covered. This all helps to minimise energy use at night. Evaporation is reduced, meaning the air-handling units have to work less hard. A positive knock-on effect!
“It’s a project we’re proud of from a construction point of view,” says project manager Steven Beyaert. “Many swimming pools feel enclosed, but this complex is perfectly visible beside the Leie and the
railway line. What’s more, the building flows seamlessly into the terraces with a bar around the outdoor pools and the artificial grass sunbathing lawn. We can also be proud of what we’ve achieved aesthetically.”
Question about this story? Ask your question
Who worked on it
LAGO Kortrijk Weide in Kortrijk