Largest-ever timber trusses for an industrial construction project in the Benelux
Text Kris VandekerckhoveImage edibo

Group ADW, an importer and transporter of fruit and vegetables, is expanding. The plans include brand-new refrigerated storage areas, a transport hall and offices. But the real showstoppers are the seven enormous timber trusses, with their dizzying dimensions. These impressive structural elements caused a sensation both on site and on the road to get there.
edibo from Lommel was responsible for the project, from the foundation works through to the façade finishing. The contract was divided into three phases. Together, they form a single structure of almost 12,000 m², built against Group ADW’s existing buildings at its site in Sint-Katelijne-Waver. “Phases 1 and 2 focused on the refrigerated storage areas, including cold rooms and ripening rooms. The roof structures in the first two phases consist of steel trusses fabricated in our own workshop. These were later concealed behind special insulated sandwich panels, known as cold-store panels,” explains project manager Wouter Van Asbroeck. For phase 3, the new transport hall with loading bays and office space, the client opted for a more architectural solution: seven substantial timber trusses.

Virtual scenarios
“There were several reasons for that choice,” explains structural engineer Raf Steensels. “One was the architectural and aesthetic effect. A timber beam stands out and has a certain natural appeal. The smooth finish also means dirt and dust particles have nowhere to catch or settle. A steel truss has more nooks and crannies, and therefore a greater risk of dust build-up. That is something to avoid in a food industry setting. Finally, there is the transport aspect: concrete beams would simply be too heavy to transport and lift. They would also require stronger foundations.”
To achieve the full span, seven timber trusses measuring no less than 45 metres in length were required. They are the largest trusses ever produced for an industrial construction project in the Benelux. Raf Steensels: “Most of the communication between the supplier, LTS Belgium, and edibo took place in the project’s 3D environment. We designed the overall structure, and the subcontractor added every bolt, every screw and every penetration to the drawings. The same applied to the point loads. Large refrigeration units were to be suspended from the centre of each truss. Could the trusses withstand these point loads at their most unfavourable position? We worked through the scenarios one by one virtually before proceeding with final production.”
A challenging installation
Raf Steensels: “And the hardest part was still to come: the actual installation on site. After an impressive overnight transport, every step of the installation had to be carefully coordinated. First, we had to check the load-bearing capacity of the columns and the foundations beneath them, on which the timber trusses rest. But also: had all potential obstacles on site been taken into account? Could the crane boom manoeuvre through the necessary angles and turns during lifting? In short, there were many issues to resolve, which we successfully managed through thorough preparation and extensive virtual consultation with the manufacturer.”

On schedule
Wouter Van Asbroeck: “On this project, our expertise across several industrial sectors has been key to keeping everything on schedule to date. Our experience also tells us that certain considerations come up time and again with refrigerated storage areas of this kind, such as achieving an even tighter seal between the insulation, façades and roof, or using a specific type of roof waterproofing to prevent condensation.”
“We can also draw on our strong in-house expertise to take a firm hand in delivering this project. And, for me personally, this is the first time that a number of subcontractors have actively provided digital input and feedback in the project’s 3D environment. It has been a welcome introduction, and one I’d be very happy to repeat!” concludes Wouter Van Asbroeck.
Question about this story? Ask your question
Who worked on it
Transporthal Group ADW in Sint-Katelijne-Waver, nieuwbouw
- clientPetrova Plants
- architectArchiteam
- main contractoredibo
- timber trussesLTS Belgium
Keep following this
Get an email when a new story is published. No account needed.
- ProjectTransporthal Group ADW
- SubjectConstruction projects
- CompanyPetrova Plants
- CompanyArchiteam
- Companyedibo
- CompanyLTS Belgium