New office building is the result of extensive circular construction

In mid-May, ’t Centrum, Kamp C’s new office building in Westerlo, officially opened its doors. According to the client, you will not find a more circular office building anywhere in the Benelux: it is made from reusable and ecological materials, can be fully dismantled and rebuilt in its entirety, incorporates various products and systems linked to circular financing or revenue models, and was delivered following a circular tendering process. With ’t Centrum, Kamp C aims to show how circular construction can be achieved, and to raise awareness and inspire the construction sector and private individuals to embrace this sustainable building principle.

The claim that nowhere in the Benelux will you find an office building where circular construction was pursued so extensively is a bold one, particularly as there is not yet a real benchmark against which to substantiate it. Even so, it seems to come very close to the truth. The focus on circular construction began with the tendering process. Kamp C also gave this a circular focus, basing the selection criteria on circularity rather than the lowest price and seeking a consortium that would work together from day one to achieve greater efficiency and innovation. Kamp Circulair was ultimately selected, a team of seven companies: Beneens, west architectuur, Streng-th, Muurtuin, Tenerga, TENgroup and VITO.
The result is a three-storey building with a total floor area of 2,400 m², made from reusable and ecological materials, some of which are linked to circular financing and business models. The project also focuses on sustainable energy supply and water management. In addition, ’t Centrum can easily be extended, dismantled and rebuilt, thanks to a design based on a modular, standardised 5 by 5 metre grid.

New and reclaimed materials
The office building, characterised externally by large windows, timber and a green wall, is constructed from standardised modular walls, floors, columns and beams made of timber, including laminated timber and CLT. It has a cement-free foundation made of gravel, sand and binder, developed specifically for ’t Centrum as part of the Interreg project URBCON, together with the cement-free screed. The structure was erected in just one week. Every other material is reusable or ecological, including JUUNOO walls and Ecoschelp floor insulation.
Several materials had already served a first life in another project. The carpet, for instance, is recycled, and its tiles were laid in a random colour pattern to make them easier to replace. ’t Centrum also features a staircase reclaimed by Beneens from a renovation project at AB Inbev. The timber cladding came from the event venue Hangar 26 in Antwerp, which is being renovated. The Antwerp-based sheltered workshop KUNNIG gave the timber a thorough makeover. Kamp C reclaimed the furniture from its visitor centre.

Materials passport
All materials used have been physically tagged and recorded in a Building Information Model (BIM), to which the materials passport is directly linked to facilitate their reuse. QR codes will also be added shortly, giving visitors, whom Kamp C hopes to use the building as a source of inspiration for anyone looking to adopt circular construction, quick access to the necessary information about each material used. “Building with a deposit value is now possible,” explains contractor Joeri Beneens. “You could put out a tender if you ever wanted to demolish this building, and there would be genuine bids, because everything can be reclaimed and reused.”
’t Centrum also uses an innovative building management system. This helps optimise energy use and keep it as low as possible, while also enabling preventive maintenance and thereby extending the building’s service life. The building management system itself uses wireless sensors, avoiding many metres of cabling and making the system easy to expand or scale back. With that in mind, all the building services have also been left exposed.

Shallow geothermal energy and water purification
A BEO field with eighteen boreholes reaching 145 metres deep is connected to a collector and heat pump, providing heating and cooling through shallow geothermal energy. The system eliminates the need for fossil fuels and guarantees energy consumption of less than half that of conventional heat pumps, which use the outside air as their heat source. Cooling and heating are supplied through an as-a-service model. Such a model is considered more circular because it often aims for the manufacturer to take back the products, in this case the heat pumps, for example, giving some or all of them a new lease of life. The smart LED lighting is also supplied as a service.
Muurtuin’s vertical greenery, including the green wall on the building’s façade, purifies greywater from sources such as washbasins, showers and washing machines, allowing it to be reused for flushing toilets. The plants in the green walls were selected to withstand the soap residues that may be present in the greywater.

Favourable LCA
A life cycle assessment (LCA) shows that the building’s environmental impact is very low. Over its entire service life, it saves around 800 tonnes of CO2, covering both embodied and operational carbon, compared with traditional buildings of a similar size. This is equivalent to the carbon captured by around 70 hectares, or a hundred football pitches, of forest. A doctoral study at the University of Liège found that a copy of ’t Centrum built in concrete or steel would emit three and four times more CO2, respectively. The project partners are confident that ’t Centrum will be carbon neutral or even carbon negative after just a few decades.

Demonstrating design for disassembly
“Because we worked with so many reclaimed materials, the design was never really finished. It is only finished today,” says Sarah Teeuws, architect at west architectuur. “But for us, the project does not end here. Given the adaptability and dismantlability of ’t Centrum, the project actually has a lifespan of more than a hundred years. The construction process accounted for only a few years on that timeline.”
The architect also says that Kamp C intends to demonstrate dismantlability in practice in the future. “The project actually comprises four buildings. Buildings A and B, which were built adjoining one another, are now complete. Kamp C plans to build block C one day, adjoining the existing block, drawing on insights gained during the construction and use of blocks A and B. After that, it wants to dismantle block A and use it to build block D. However, it is not yet certain whether this plan will be carried out, and alternatives involving mock-ups are also being explored.”
“Certain circular elements of ’t Centrum, such as the structure, are already market-ready and could soon appear in other construction projects. More research is needed into other materials and technologies, but ’t Centrum provides the ideal starting point,” adds Kathleen Helsen, deputy of the Province of Antwerp.
Question about this story? Ask your question
Who worked on it
- ClientKamp C (Westerlo)
- Architectwest architectuur (Westerlo)
- Main contractor(s)Beneens (Olen)