Construction projects

Prestige project calls for optimised foundation and earth-retaining solution

Dit prestigeproject was niet alleen uitdagend op technisch vlak, maar ook vanuit logistiek oogpunt.
Dit prestigeproject was niet alleen uitdagend op technisch vlak, maar ook vanuit logistiek oogpunt.

The construction of Etterbeek’s new administrative centre was no mean feat.

The challenges began with the foundations and retaining structures for the excavation, for which specialist Franki Foundations developed an optimised solution. Combined with the logistical challenges posed by the project, this was no easy task.

A brand-new town hall, a police station, a Public Social Welfare Centre and an adjoining residential building: the scale of the new administrative centre on the busy Kazernenlaan in Etterbeek is impressive. It is therefore no surprise that the excavation on the site of the former military hospital was also enormous. “We were tasked with developing a complete foundation and retaining solution on behalf of main contractors BPC and CIT Blaton. After considering various factors,
we opted for a combination of different techniques,” says Tim Eggermont, Head of Production at Franki Foundations. 

“We installed 27 foundation piles, each with a usable load-bearing capacity of up to 150 tonnes,” says Tim Eggermont.

Hybrid solution

“For economic and technical reasons, including more efficient phasing, a lack of space for large machinery in certain areas and specific site conditions, we did not opt for a conventional continuous secant pile wall, but for an optimised hybrid solution,” explains Tim Eggermont. “Along the side where the basement extends down to level -2, we installed 240 linear metres of anchored secant pile wall, requiring 3,850 metres of piling, 1,500 m³ of concrete, 50 tonnes of steel, 106 anchors (1,300 metres in total) and 60 tonnes of cement. Where the basement does not extend below level -1, we used soil-nailed walls, comprising a combination of passive anchors, reinforcing mesh and sprayed concrete. We also installed 27 foundation piles, each with a usable load-bearing capacity of up to 150 tonnes.”

“Where the basement does not extend below level -1, we used soil-nailed walls,” explains Tim Eggermont.

A logistical puzzle

This prestige project was challenging not only from a technical perspective, but also logistically. The site is in the heart of Etterbeek, a densely populated area with heavy traffic. “We needed special transport permits to get our machinery to the site. One side street was also kept clear as a temporary waiting area for loading and unloading equipment,” says Tim Eggermont. “Another unusual feature was that, in certain places, the existing masonry wall was used as part of the soil-nailed wall. The nails pass through this wall. Finally, an interesting detail is that our foreman and machine operator was promoted to site manager after the project, thanks to his extensive
expertise in secant pile walls and other retaining techniques. This is further proof that skilled specialists at Franki Foundations are given every opportunity to progress in their careers!”    

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectConstruction projects
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.