Seamless expansion of warehouse and office space

To mark its 25th anniversary, Linea 2000, the company behind the renowned DOMO electrical appliance brand, moved to new premises in Herentals at the end of 2011. Less than a decade later, the site was expanded with 900 square metres of office space and 5,600 square metres of warehouse space. A fine example of workmanship by ASK Romein, which seamlessly connected the shell of the existing building to that of the new extension.

The story of Linea 2000 reads like a modern fairy tale. The successful family business began in 1986 as an importer of domestic electrical appliances. It soon launched its own brand: DOMO, which has become a leading name in kitchen and household appliances thanks to its innovative products and excellent value for money. Although Linea 2000 places great importance on its roots in the Campine and is keen to respond to local needs, its ambitions extend beyond the Belgian market. The company aims to build DOMO into a strong European brand. A substantial expansion of its existing warehouse and office space was therefore needed.

Building in the midst of the coronavirus crisis
ASK Romein, a contractor specialising in construction and steel construction, was responsible for the weatherproof shell, excluding the office windows and doors. Linea 2000 took care of the fit-out and external works itself. “We built the new section against the existing rear façade, which was clad in traditional profiled steel sheeting,” says Niels Vorselaars, project manager at ASK Romein. “The challenge was to turn it into a completely new fire wall, as the new section forms a separate fire compartment. At the same time, the existing warehouse remained in use, so we had to replace the profiled steel sheeting with new concrete panels in stages. The
façade had to be completely sealed at the end of each working day.”
“The fact that the project started in February 2020, just before the coronavirus crisis, naturally made things more difficult. The measures imposed by the government at the time brought construction to a standstill for several weeks. This created serious challenges in terms of planning and organisation. The precast elements also took longer to arrive than expected, as the manufacturers were experiencing delays too. Despite these unforeseen challenges, we completed the shell at the end of September
2020.”

Complex precision work
The extension to Linea 2000’s premises is 100 metres long, 71 metres wide and 12 metres high. To follow the shape of the plot and make the most of the available space, the rear of the building features several stepped sections. “The architect, who had also designed the existing building, wanted to create a unified whole. That is why the structure combines concrete with steel purlins. The same materials have been used throughout the exterior. The ground-floor sections of the façade are made of white concrete panels, while the upper floor is clad in black profiled steel sheeting, including a continuous strip window in the office section,” explains Niels Vorselaars.
“Although the existing structure had been designed to accommodate an extension, connecting it to the new structure was a complex precision task, especially as we first had to build the fire wall between them. As a result, we had to tilt the 34-metre-long IV roof beams into the integrated recesses using two crawler cranes. They were transported to the site under special night-time transport arrangements. To top it all off, we also installed a 40-metre-long walkway directly connecting the existing and new office sections. This steel structure was fixed to the concrete structure at a height of six metres, and an additional doorway was created. All in all, it was a great and challenging project, and we worked very well with the client and the architect!”
Question about this story? Ask your question
Who worked on it
- ClientLinea 2000 (Herentals)
- ArchitectWilma Wastiau (Westerlo)
- Main contractor(s)ASK Romein (Malle)