Swimming pool for sports clubs and the wider public

An official 50-metre competition pool, a teaching pool with a deep movable floor for diving clubs, and a leisure area.
With this range of facilities, the new Zwembad Brigitte Becue meets all the needs of swimmers and water sports enthusiasts in Ostend. And that is before we mention the attractive cafeteria, the panoramic view over the golf course and the social housing apartments above the sports facilities …

Since 1 May, the City of Ostend has been welcoming water sports enthusiasts and swimming fans to its brand-new municipal pool. It has been aptly named Zwembad Brigitte Becue, in tribute to the Ostend swimming champion and Belgian breaststroke star. “A proper competition pool was a must,” says Dieter Haemers, Senior Architect at B2Ai architects, which teamed up with Dutch practice VenhoevenCS for the project. “Of course,
the building programme also included many other functions. Apartments had to be built, and accessibility was another key consideration. We addressed this in a design that places residential units above the pool facilities. The pale brickwork complements the sandstone-coloured buildings nearby, while standing out thanks to its slightly lighter shade. The architecture is light and open, and perfectly tailored to its surroundings on every side, from the entrance square and cafeteria to the panoramic view of Wellington Golf from the pool. The use of concrete on the pool side reinforces this dialogue between the building and its surroundings.”

Modern swimming facilities
Like many swimming pools in cities and towns, the former Ostend pool was outdated, with its technical systems and energy efficiency no longer up to scratch. More than just a replacement, the new project is an upgrade that brings together a range of functions and caters for a broad cross-section of swimmers, from dedicated athletes, whether or not they belong to a club, to water-loving fun-seekers of all ages. A leisure area has been designed for the latter group. The two slides and climbing wall, among other features, offer plenty of challenging aquatic fun. “Our main focus was on the many swimming and diving clubs in the area,” says Dieter Haemers. “The 50-metre pool is an official competition pool, complete with a stand for supporters and visitors. We have also built a modern teaching pool with a movable floor. It can be lowered deeper than in an average pool, giving diving clubs a great place to train.”

The pool area is anything but cold and bare. Perforated timber roof decking helps to dampen some of the noise made by swimmers. The panels also make it possible to span large distances. To reduce background noise further and achieve a comfortable acoustic level, one wall was finished entirely with spray-applied plaster, allowing swimmers to relax and exert themselves in comfort in their new pool.
For contractor Stadsbader, which formed a temporary joint venture named Sportsbuilders with Olco Sportsphere, this multi-purpose pool was a baptism of fire. “For our first proper swimming pool project, we too brought in a Dutch expert, particularly for the building services,” explains site manager Yves Van Petegem. “There were, of course, several aspects to consider during construction. Waterproofing, for example. We build plenty of watertight structures, including basements, but the standards are obviously much higher for a swimming pool. We cast the overflow channels together with the walls, and all the tiling was finished with epoxy grout.”

Sport, leisure and living on one site
The design competition also called for social housing on the same site. The architects opted to place the apartments above the pool building. “This was a choice in favour of compact construction and optimal accessibility across the site,” explains architect Dieter Haemers. “The two residential blocks have completely independent access and are finished with traditional materials and energy-efficient systems. There are 22 apartments in total. Like visitors to the pool, residents can park their cars in the underground car park. They also benefit from the lively atmosphere and facilities of the new sports site.”
Bringing the different functions together in an attractive and practical concept called for the right expertise in both design and construction. The architects and contractors pooled their skills and experience to complete the project successfully. Site manager Yves Van Petegem says: “There was a gap between the construction of the pool building and the apartments. That became a bottleneck. We could not complete the pool waterproofing until the apartments were ready. Clear, carefully considered planning and open communication with all the construction partners ensured that the work nevertheless progressed smoothly.”

For architectural duo B2Ai architects and VenhoevenCS, this was a new chapter in a successful partnership. They first worked together several years ago on De Nekkerpool in Mechelen. “VenhoevenCS in the Netherlands has been designing swimming pools and sports buildings for some time. Last year, they won the commission for the new swimming arena for the 2024 Olympic Games in Paris. It was a great opportunity for us to draw on their expertise for our project. When we were awarded this commission, working together again was not even a question, it was the obvious choice,” says Haemers. “We hope to take on more projects like this in the future, with an open mind and creative ideas. All the construction partners were on the same wavelength, and you can see that in the excellent end result.”
Holvoet Gebroeders: Bespoke joinery
Humid air and chemical exposure, including chlorine. It is common knowledge that wood and swimming pool buildings are not an obvious combination at first glance. Unless, that is, you have the knowledge and expertise to make them work together. Holvoet Gebroeders (Ingelmunster) carried out the bespoke joinery for Zwembad Brigitte Becue. The internal doors in the pool area are made from solid-grade laminate with PU. Together with the padauk block frames and bluestone thresholds, these elements make the doors more resistant to the pool atmosphere. The internal doors in the apartments are standard paint-grade doors. Holvoet Gebroeders also installed a considerable number of technical doors, including fire-resistant and moisture-resistant internal doors. The standout features of the project, however, are the bar and reception desk. These large interior elements are built from HPL panels and finished with sliding glass sections and solid oak counters. The architects’ original design was fine-tuned by the entire construction team during an intensive preparatory phase. Holvoet Gebroeders prefabricated as much as possible, ensuring smooth assembly on site. The bar can also be closed off completely using roller shutters, which are integrated invisibly into the ceiling. These too were installed and meticulously finished by the experienced joiners.
Im Press: Signage
The Kortrijk-based family business Im Press was responsible for signage in and around the swimming pool complex in Ostend. It worked closely with the architect, the City of Ostend and contractor Stadsbader. “Together, we developed a complete concept. Which materials and signs should be used, where should they go, and where should they be repeated? For the new pool in Ostend, we handled the emergency signage and evacuation plans, as well as the wayfinding,” says Olivier Verstraete, project manager at Im Press. “We used engraved plastic that can withstand swimming pool environments and also fits perfectly with the architectural vision for the building.”
All Im Press signage is made to measure, and this project was no exception. Im Press also provided anti-collision markings on the windows, in the pool’s corporate colours. “We incorporated a motif so that it would fit perfectly with the surroundings. We also supplied the façade lettering. This was made from painted aluminium at the architect’s request,” adds Olivier Verstraete. Im Press has the necessary expertise in swimming pool projects. When selecting materials and developing designs, it takes account of the humidity, chlorine and temperature conditions in swimming pool buildings. The company is also active in many other sectors, including office complexes, residential care centres and leisure facilities.
PROJECT DETAILS
Client
Zwembadbeheerder FARYS on behalf of the City of Ostend
Architect
B2Ai architects (Roeselare) and VenhoevenCS (Netherlands)
Main contractor(s)
Sportsbuilders (temporary joint venture between Olco Sportsphere and Stadsbader)
Een zakelijke vraag aan Stadsbader? Get in touch
Who worked on it
Zwembad Brigitte Becue in Oostende
- contractor
Stadsbader - clientStad Oostende
- architectB2Ai architects
- architectVenhoevenCS
- main contractorOlco Sportsphere
- houten maatwerkHolvoet Gebroeders
- signalisatieIm Press
Keep following this
Get an email when a new story is published. No account needed.
- ProjectZwembad Brigitte Becue
- SubjectConstruction projects
- CompanyStadsbader
- CompanyStad Oostende
- CompanyB2Ai architects
- CompanyVenhoevenCS
- CompanyOlco Sportsphere