To meet global demand for sea salt, ZOUTMAN built a new production tower at North Sea Port in Ghent. This will increase the Roeselare-based company’s production capacity by 150,000 tonnes per year. At 64.5 metres, the new production tower is the tallest of its kind in the world. At this site, ZOUTMAN will focus on producing sea salt without additives.
Stranger Architect & Engineering was responsible for designing the new salt tower. BM Engineering acted as the engineering consultancy for designing the building structures, fully in line with the specific requirements of the salt-processing plant. To ensure the project ran smoothly, everything was coordinated in BIM. The initial concept for the ZOUTMAN production tower in Ghent was based on a standard beam-and-column structure. Drawing on its many years of experience in industrial construction and expertise in high-bay warehouses, contractor Alheembouw proposed an alternative approach. “We abandoned the plan to use precast floor slabs and opted for beamless floors cast in situ. With a conventional beam-and-column structure, the columns take up a lot of space along the external façade. The beams also limit where openings can be made, as you cannot drill through them, for example to attach services to the ceiling, and you have to take account of the space between the beams,” explains Alheembouw site manager Thomas Vermeersch.
The West Flanders contractor aims to create the most functional possible building on every project. Its experienced team works proactively with the client and plans every stage of the construction process in detail. “In our proposed system, the flat floor slabs are supported by the load-bearing external walls and central columns. This allows us to strike the formwork sooner, while the client benefits from greater clear height and more freedom to create openings in various locations. For the external façade, we built a cavity wall with stainless steel sandwich panels to provide good insulation.”

Working at a challenging height
To develop its concept, Alheembouw called on structural engineering consultancy Establis. Engineering consultancy BM Engineering delivered the three ancillary buildings and determined where openings could be made in the tower and the loads on the floor slabs. Establis incorporated BM Engineering’s requirements into Alheembouw’s design. “We worked closely together throughout the entire construction process,” Thomas Vermeersch continues. “Casting the floor slabs in situ means you can create service openings anywhere without compromising structural stability. In itself, this is a standard method of construction, but the height of the tower made it fairly complex. The new production tower is 64.5 metres high and has ten storeys. The top floor is 55.5 metres above ground. All the work had to be carried out using the tower crane and a man-riding cage on the outside of the façade, for example to lift materials to the top or spray the joints.”
Precast beams installed upside down
A further challenge was installing 22 plastic silos on the third floor, at a height of 20 to 28 metres. Thomas Vermeersch explains: “The silos stand on load cells and are positioned on a grid of beams. They had to be installed with great precision, to a tolerance of just 2 millimetres. The supporting surface needs to be exceptionally level to ensure the contents of the silos can be weighed accurately. We therefore chose precast beams from Betca, which we turned through 180 degrees on site so that the flat side faced upwards and the levelled face of the beam was underneath. This allowed us to work much more accurately.” For the floor above the silos, Alheembouw used 13-centimetre-thick self-supporting precast floor slabs. This meant no temporary propping was needed beneath the floor slab. “As our supplier could not manufacture them, we made a precast casting table on site and cast the 32 precast slabs there.”
Finally, the concrete mix required careful consideration. The special concrete mix had to withstand the salty environment. “Trans-beton had the best type of concrete for this. We also had its specific mix extensively tested by KU Leuven to guarantee the tower’s service life. The same concrete mix was used for the precast beams. This project raised a number of interesting challenges. Thanks to close collaboration between all the parties involved, we found good solutions and managed to stay as close as possible to the tight schedule and planned budget.”
Question about this story? Ask your question
Who worked on it
- ClientZOUTMAN (Roeselare)
- ArchitectStranger Architects & Engineers (Antwerpen, Kortrijk)
- Main contractor(s)Alheembouw (Oostnieuwkerke)
Keep following this
Get an email when a new story is published. No account needed.
- SubjectConstruction projects