TSG | Turnhout: TSG moves into new office and warehouse space

At the new regional business park on Veedijk in Turnhout, TSG, formerly Tokheim Solutions, has taken up occupation of its new offices, warehouse and production space. The complex has an open character, comprises three storeys and covers 2,160 m².
TSG already had a partial presence in Turnhout. The group’s administrative and commercial services were based there, while its logistics department was located in Bladel in the Netherlands. Given economic developments and the company’s own growth, it seemed more practical to bring the two entities together. It therefore set out to find a suitable site. “With the help of contractor Cosimco, which already had extensive experience on the local business park, TSG was able to buy a suitable 8,700-square-metre site from the Intercommunale van de Ontwikkeling van de Kempen (IOK), not very far from its existing premises,” says Sebastian Mortelmans of mortelmans van tricht architecten.
The concrete frame and terraces also provide solar shading.

Logistics in motion
TSG, which invested around 7 million euros in the new buildings, is Belgium’s market leader in the equipment, automation and maintenance of petrol stations. It is also Kärcher’s strategic partner for car wash equipment at petrol stations. The company has 165 employees, including those transferring from Bladel. Many of them are technicians who are on the road almost constantly. They will face many challenges in the near future, as petrol stations increasingly offer alternatives alongside conventional fuels, such as compressed natural gas (CNG), liquefied natural gas (LNG) and charging facilities for electric vehicles.
“Technicians in the field digitally submit a list of the items they need. On that basis, their colleagues in Turnhout put together tailored packages, which are distributed overnight. The logistics team can access the field technicians’ vans, remove the parts to be repaired or replaced, and put in the new and repaired items. The next day, the technicians find everything they need for that day in their vans,” says the architect.
The office area is very open, giving TSG employees panoramic views.

Contrasting forms
The architects designed an open, three-storey office building, with adjoining workshops and a multi-level warehouse. The warehouse and workshops are clad in dark steel façade panels, which continue along the plinth of the office volume. A contrasting white concrete volume sits above this plinth. The concrete frame is fitted with wide, floor-to-ceiling windows set back from the façade. This creates sheltered terraces and means the concrete also acts as a fixed solar shading device. Visually, the building stands out strongly from other recent office buildings, where extensive glazing often strips the concrete or metal frame of any aesthetic significance.
TSG regularly welcomes customers and other visitors, who can see how the company operates. Through the main entrance, they reach a semi-public open space with a reception desk. “They find themselves straight in the beating heart of the company,” says Mortelmans. “Employees have a second entrance, with quick access to the changing rooms and workshop.”
The warehouse and workshop form an enclosed volume.

Extra attention to acoustics
The layout of both floors is fairly conventional. Stairs and lifts, the kitchen and sanitary facilities are grouped in the building’s concrete core. Offices are arranged around the core, allowing plenty of natural light in and giving employees panoramic views of the surrounding area. A glazed walkway connects the office volume to the adjoining warehouse, facilitating collaboration between the workshop and office.
“With so many people working together in a relatively small area, we had to give extra attention to acoustics. That is why we installed fitted carpet,” says the architect. “And we installed acoustic partition walls on the second floor,” add Jack Berben, commercial director, and Jonathan Van Loon, project manager at Cosimco. The data cabling is integrated into the floor, while Interalu chilled ceilings provide heating and cooling.
The building services plant is on the roof of the office building, while the warehouse roof is fitted with photovoltaic panels.
The entire complex was built in just eight months.

Warehouse
The warehouse’s steel lattice girders span 36 metres, allowing for a highly flexible layout. The polished concrete floors at ground level can support loads of up to 1 tonne per square metre. Packages for the technicians are assembled on the upper floor. “We installed a concrete blockwork fire wall between the office and the workshop.” Like the office plinth, the warehouse and workshop façades are finished with metal sandwich panels. This proved to be a more budget-friendly solution than the originally planned textured concrete panels.
Liquid-tight
Various polluting liquids can leak from dismantled petrol tanks and their associated infrastructure. That is why not only the warehouse but also part of the paved area behind the building has a liquid-tight floor. Beneath this area is a 420 m³ concrete tank that supplies the sprinklers. “In principle, it only needs to be filled once with mains water,” explains Mortelmans. “TSG uses rainwater collected from the roof to flush the toilets and water the landscaping.”
Cosimco and its subcontractors managed to build the entire complex in just eight months. “Even though TSG changed the warehouse layout while construction was already well under way,” recalls Van Loon.
Words Koen Mortelmans Photography Simon Van Ranst Photography
TECHNICAL DETAILS
Client TSG (Turnhout)
Architect mortelmans van tricht architecten (Antwerp)
Main contractor(s) Cosimco (Kontich)
Project partners speak
Peritas: Building services consultant
Consultancy Peritas designed all the building services installations for TSG’s new building. “Specifically, this included four-pipe heating and cooling and air handling via climate ceilings, electrical installations, lifts, sanitary facilities, ESFR sprinklers and even the kitchen equipment,” says Marijn Wauters of Peritas.
“The Interalu climate ceiling in the office area is connected to six-way valves. This ensures thermal comfort and allows each room to be set individually for cooling or heating. The chiller is variable-speed controlled. Ventilation is provided by an air handling unit with heat recovery on the roof,” says Wauters. “The warehouse is heated by a combination of gas-fired unit heaters and radiant tubes.”
Peritas was established in 2010. In addition to its head office in Wilrijk, it has regional offices in Ghent, Brussels and Ostend. “Our rapidly growing team now numbers around thirty.” Peritas specialises in EPB reporting and safety coordination, energy projects, building services studies and structural engineering. “We work in both the private and public sectors, for everyone from private individuals and property developers to public authorities and institutions such as social housing companies.”
Peritas carried out, among other projects, the building services design and follow-up for all services in the extension of Woon- en Zorgcentrum Sint Jozef in Rumst, the offices of
Provikmo in Herentals, the full renovation of 2 AGSO schools in Antwerp and Merksem, the new leisure centre in Edegem and the conversion of Kasteel ter Rijst in Heikruis.