YUST, Berchem | A refreshing co-living concept in a prime location

YUST, Berchem | A refreshing co-living concept in a prime location

Another striking restoration and extension project was recently completed close to Brouwerij De Koninck and the Electrabeltoren. YUST (Young Urban Style) is not only an unconventional structure from an architectural perspective, it also stands out for its underlying social dimension. The project introduces forms of living that are not yet, or at least not systematically, available in Flanders.

Berchem yust vakblad vlaanderen

The original street façade was retained. It contributes significantly to YUST’s loft-style feel and authenticity.

The existing buildings along Coveliersstraat were already listed in inventories of valuable architectural heritage. They were built in the late nineteenth and early twentieth centuries by Ateliers de Téléphonie et d’Electricité, later known by the more language-neutral name Atea. After Atea moved to Herentals, the buildings were used by Brouwerij De Koninck. “Mainly for storage,” says Stéphane Verbeeck, CEO of client Gands. “As our own office is in the same area, we could see that the former Atea buildings had much greater potential. When the brewery merged with Moortgat, we were able to buy them.”

For a young audience

Gands approached POLO Architects and contractor Vanhout to renovate and repurpose the historic buildings, and extend them, particularly upwards. This was done with the utmost respect for the existing brick façades, adorned with wall anchors and natural stone. “It wasn’t just concern for the past that motivated us,” says Verbeeck. “We’re targeting a young audience here. Today, young people want authenticity in their living experience. That’s not something you find easily in a new-build project. By using vintage interior features and second-hand furniture, and paying close attention to detail, we were able to preserve that valuable sense of authenticity.”

Berchem yust vakblad vlaanderen

Residents can gather in a cosy courtyard garden.

Since the project was completed, YUST has offered 75 fully furnished studios, each with its own bathroom. Residents share a number of communal spaces. “We have three rental rates, for stays ranging from one month to a year.” A hotel with 153 beds is located on the first floor. “A hundred guests can stay in luxurious ‘dorms’ (shared dormitories), with towels and fresh linen, and separate bathroom facilities for each room. The remaining beds are in what you could call traditional hotel rooms.” Almost all the interior features were specially designed for YUST.

Compact living in a prime location

Berchem yust vakblad vlaanderen

The historic buildings have not only been renovated, but also extended, particularly upwards.

All residents can make use of communal facilities and services, including a roof terrace, shared bicycles, meeting rooms, a co-working space and a laundry service. The hospitality facilities are open to the public. “With YUST, we’re responding to growing demand for more compact homes in prime locations and flexible short-term living solutions.” Verbeeck also dreams of a European co-living network, whose members could temporarily exchange their (well-located urban) homes as part of a ‘shared’ economy.

Exceptional

“Even for a large and experienced contractor like Vanhout, this was an exceptional project,” says project manager Philip Smits. “The operator was still working out the exact details of the homes, and therefore the floor plans, while construction was under way. Given the repetitive nature of the building and the logistical constraints of its city-centre location, we made the most of extensive off-site prefabrication. This included prefabricated hollow-core walls, precast floor slabs, stair cores, building services and steel-frame walls, external joinery, façade cladding, prefabricated bathroom units and fixed furniture.”

Berchem yust vakblad vlaanderen

Arnt Grützner: “The advantage of the high construction speed was decisive in our proposal to use light-gauge steel framing.”

All this was translated into a BIM model. The steel frame was modelled in 3D in advance. “Using light-gauge steel framing on the four top floors proved a particularly significant challenge. Cold-formed steel sections are made to measure in the factory and assembled into 2D wall elements, complete with the necessary bracing and openings for the building services. The steel frames and prefabricated bathroom units in particular made this site very different from a traditional building site. Logistically, the challenge was to deliver materials to the site at the right time. Storage space was extremely limited, so we had to process incoming materials quickly.”

Extensive design work

The steel-frame walls, together with the steel composite floor decks, form the structure of the entire upper section. “This required extensive design work to coordinate with the other subcontractors and ensure that the client’s various fire safety and acoustic requirements were met without compromising the architect’s design. Coordinating the service penetrations to the shafts with the prefabricated bathrooms also proved a considerable challenge.”

Vanhout carried out an extensive 3D scan of the existing front and rear façades to ensure that the sections to be renovated aligned as closely as possible with the new prefabricated hollow-core concrete walls and window openings. An innovative approach. “We learned from this that it’s best to wait until the elements to be demolished have been removed before carrying out a scan like this,” says site engineer Arnt Grützner (Vanhout).

Alternatives assessed

As main contractor, Vanhout took a highly proactive approach, suggesting various technical alternatives and other changes to the original plans. “We had been in contact with client Gands and architectural practice POLO since 2015 to help investigate which construction method would be most suitable for this project,” Grützner recalls. “Initially, we looked at using cross-laminated timber (CLT). The look of the timber and its renewability as a sustainable building material were very appealing, but the cost was too high. Building in calcium silicate blockwork and concrete is cheaper than building in CLT, but involves more transport and a longer construction period.”

After various cost calculations and studies of alternative designs, the building contract was signed in April 2017. “Given the highly suitable repetitive studio layout, we also analysed various prefabrication systems. Ultimately, the benefit of a faster build, which meant getting the shell watertight and windproof sooner, tipped the balance in favour of proposing light-gauge steel framing.”  

Question about this story? Ask your question

Wie aan YUST werkte

  1. clientGandsIn this story
  2. architectPOLO ArchitectsIn this story
  3. contractorVanhoutIn this story
  4. haardenspecialistAMA HaardenMentioned in YUST, Berchem | Designer fireplace takes pride of place in entrance hall

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectYUST
  • SubjectConstruction projects
  • CompanyGands
  • CompanyPOLO Architects
  • CompanyVanhout
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.