“Industrial construction has become a case of having to do everything at once”

Text Tim JanssensImage Dieter Meyns

Van links naar rechts: Luc Ysebaert, Maarten Allijns, Charles Valcke en Timothy Cuypers.
Van links naar rechts: Luc Ysebaert, Maarten Allijns, Charles Valcke en Timothy Cuypers.

Speed, efficiency and functionality have always been key in industrial construction. Today, however, there are many other factors that can make or break a project. And a number of wider challenges make it far from easy to bring everything together, including sharply rising construction costs, a shortage of land and protracted permitting processes. What’s more, futureproof construction can no longer ignore major trends such as modular and circular building. Plenty to discuss, then, in a lively round-table conversation with four industry experts, who were given a warm welcome at the brand-new headquarters of Louwers Mediagroep in Oostkamp.

Participants

• Maarten Allijns, managing director at Hercull
• Luc Ysebaert, commercial director at Willy Naessens Group
• Charles Valcke, managing director at Valcke Prefab Beton
• Timothy Cuypers, Business Manager Industrial Clients at Vandersanden

Maarten Allijns.
Luc Ysebaert.
Charles Valcke.
Timothy Cuypers.

Good morning, gentlemen. Let’s get straight to the point: is industrial construction more complex today than, say, ten years ago? And if so, what are the main sticking points?

Luc Ysebaert: “Complex is a strong word, but things are certainly different. As well as the building structures themselves, which have generally become taller, wider, heavier and, in some cases, multi-storey, there are additional considerations such as fire safety requirements, insulation levels and sustainability standards. We are also currently in an economic downturn, and construction costs have seen huge fluctuations in recent years.”

Maarten Allijns: “Other challenges, such as the shortage of available land, add to the picture. Sustainability has also become a major factor in recent years. For us as an SME developer, that starts with making smart use of space and combining different functions, such as putting padel courts on the roofs of SME units. We also make provision for energy-efficient technologies, for example by allowing enough space for solar panels. But we don’t make them compulsory, especially as they make everything considerably more expensive and complicated, particularly if there is no immediate operational return. Industrial construction has become a case of having to do everything at once, and it is increasingly difficult to make all the elements add up, especially financially. Ultimately, it is up to the client to decide what takes priority.”

Luc Ysebaert: “There’s a reason the word ‘sustainable’ has two parts (laughs). Some clients are genuinely willing to invest in buildings with lower CO2 emissions and better sustainability credentials. This includes major logistics players who want to make their projects more attractive and futureproof through a BREEAM rating. Overall, though, they are the exception. For most, making the numbers work is already difficult enough. Suitable sites are becoming increasingly scarce, and land prices have risen dramatically over the past ten years. This means we have to build in a very different way to maintain returns. Multi-storey construction and building upwards are no longer taboo.”

Charles Valcke: “As concrete specialists, we are also seeing buildings become ever taller and heavier, with increasingly long spans to make the best possible use of space. We are now using double structures to deliver even taller precast buildings.” 

With available land in short supply, the focus is shifting increasingly towards renovation and redevelopment. Does that call for a different approach?

Maarten Allijns: “There are around 400 hectares of industrial land still available in Flanders, half of it in Limburg. Meanwhile, take-up stands at 200 hectares a year. So we will need to look again at revitalising brownfield sites. I don’t mean only contaminated sites, but old industrial sites more generally. Fortunately, there are still plenty of those. Adapt to suit, build to suit, hybrid developments: these are becoming the new watchwords. One caveat, though: renovation is not always cost-effective or straightforward when it comes to eventual resale value, so in some cases demolition and rebuilding are preferable.”

Charles Valcke: “We will also need to make better use of existing industrial sites, including by demolishing existing low-rise, less functional buildings and rebuilding upwards. Ideally, company car parks should also be located beneath or on top of the building. Finally, there are often opportunities to increase density, which would allow us to bring a great deal of unused space into use.”

Maarten Allijns:  “Planning compensation is also advisable. Zoning plans contain many purple spots, indicating ‘lost’ industrial sites surrounded by housing or other uses. The areas that municipalities no longer want to see used for industry need to be relocated to other sites where they can be developed. That is one of the key ways to address the shortage of available land.”

Functionality is obviously essential in industrial construction, but aesthetics are becoming more important too. Is it difficult to reconcile the two?

Timothy Cuypers: “That’s a good question, because as a brick manufacturer seeking to give buildings a sexy look, we are naturally very focused on aesthetics. And in my view, standing out through the overall experience of a building is crucial, even in a highly competitive segment such as industrial construction. But given the sharp rise in costs, increasingly stringent requirements and certain trends, perhaps some buildings are actually being finished more cheaply?”

Luc Ysebaert: “It depends mainly on the type of client. Retailers, SMEs, logistics developers: they all follow their own logic. Developers focused primarily on returns, or companies for whom a building is a necessary evil, simply an ‘envelope’ for what actually generates revenue, are more likely to cut back on it. But an investor who wants to give a project extra appeal won’t think twice about spending an extra €100,000 on a total budget of €10 million. If the client is also the owner and user, and/or regularly deals with external customers, that is generally another reason to invest in high-quality façade finishes. That said, in an economic downturn, with costs rising sharply, it is naturally easier to make savings here.”

Maarten Allijns: “It can also be the little things that don’t necessarily add much to the cost. For example, using white rather than grey steel decking, which is standard practice at Hercull. 

That might cost an extra euro per square metre, but it gives the building a much fresher look. Landscaping can also play an important role in the overall experience of a building. Integrating buildings into green surroundings is now the new standard.”

Timothy Cuypers: “Of course, different approaches can also be taken within a single development, which often consists of several separate units. Take a manufacturer’s site, for example. The production units, usually located somewhere less visible, are unlikely to require high-end finishes. The offices are a different matter: they are the company’s calling card to clients and part of its brand. In that case, it seems essential to create an attractive, welcoming building, with a strong experience both inside and out.”

Given the focus on speed and efficiency, standardisation and precast solutions are ubiquitous in industrial construction. Is there still room for bespoke work in this context?

Charles Valcke: “Absolutely. Precast solutions and bespoke work are not mutually exclusive. In fact, demand for specific designs is growing, and these days every project includes some bespoke elements. We are currently working on a project that involves making curved sandwich panels. Unique and challenging projects like this are more common than they used to be. Thanks to the standardisation of precast construction and the speed of on-site assembly, costs remain manageable too.”

Timothy Cuypers: “The closer the collaboration between all the parties involved, developers, architects, contractors and manufacturers, from the outset, the better projects perform in terms of efficiency and speed. That’s because everything is discussed in much more detail in advance, making special applications such as curved elements and vertical brickwork more straightforward. The two go hand in hand. That is why Vandersanden has set up a dedicated department for industrial clients. We help them incorporate our products through (semi-)automated production processes. One example is ready-to-use precast concrete panels finished with brick slips.”

Luc Ysebaert: “Standardisation and precast construction are essential for keeping projects profitable and delivering them efficiently, especially given the current shortage of skilled workers. Despite that, ultra-standardised construction has not taken off here, whereas it is much more established in Germany and the Netherlands. It is simply in our Flemish construction DNA to make our own architectural and/or building mark, however small.”

How far have new trends such as modular construction and circularity made inroads into industrial construction?

Maarten Allijns: “The realisation that these are essential to making buildings futureproof is certainly beginning to take hold, especially when it comes to modularity and flexibility in how spaces are used. And rightly so, because companies that stay in the same building for decades have become the exception rather than the rule. These days, buildings need not only to be designed efficiently, but also to be easily adapted to the needs of new users or even to a different function in the longer term. That is why open spaces with as few load-bearing columns as possible are preferred. Clear heights have also increased. They used to be 4 to 5 metres, but 6 metres is now standard.”

Luc Ysebaert: “Height records have been broken time and again in recent years. We recently achieved a clear height of 42 metres, with no intermediate floors! This is largely due to automation, which is another hot topic today. It is increasingly becoming a variation on the typical high-bay warehouse, essentially a stack of racking enclosed by four walls and a roof, designed for a single specific function.” 

Charles Valcke: “As far as circular construction is concerned, some of its principles were already being applied to extensions of existing buildings in the past, such as demountable gable walls, but recently we have gone considerably further. This year, for the first time, we succeeded in dismantling an entire precast structure for future reuse. We also make the necessary efforts in-house, for example by recycling all the production waste from our precast concrete at our own site and reusing it in our in-situ concrete. Earlier this year, we also achieved C2C Silver certification, enabling us to offer our customers real added value, for example in the context of BREEAM schemes.”

Timothy Cuypers: “At Vandersanden, we are also giving a lot of thought to making our products circular and demountable. With Pirrouet®, we have even developed a carbon-negative facing brick made from waste streams from the metal industry. It is not fired in a kiln, but hardens in a conditioning chamber through the permanent uptake of CO2 (70 litres of pure CO2 per facing brick). By also using it in a dry-stack system, without mortar or adhesive, we make it suitable for dismantling and reuse. As a brick manufacturer, we are thus doing our bit, in both a literal and figurative sense, to contribute to the circular transition.”

Luc Ysebaert: “As a leading construction company, we too are strongly committed to circular construction. We have even set up a dedicated department for it. And with The Circle®, we have developed a pioneering concrete construction concept that lets you create a modular design in 2 hours using an innovative 3D tool and a materials bank of a hundred different building blocks. A first 40,000 m² logistics building constructed entirely in this way is now standing in Liège.”

The construction and development sectors are grappling with persistent permitting problems. What has your experience been?

Maarten Allijns: “As an industrial developer, I’m careful not to complain bitterly about it. The process is indeed too slow and could be much more efficient, but compared with the residential property sector, where NIMBY attitudes are far more prevalent, we’re not doing too badly. By laying the groundwork properly and consulting proactively with the city or municipal authorities, local residents and all professional stakeholders, we can resolve a great deal. Communication and engagement are key. That is one of Hercull’s strengths, helping to improve the chances of our applications succeeding and keeping permit processing times fairly reasonable. Overall, though, it is a sticking point that appeals can be lodged too easily, blocking progress for several months or, in the worst case, even years. Fortunately, politicians are taking steps to raise that threshold. A project should not turn into a legal battle.”

Luc Ysebaert: “For us as a contractor, the saga surrounding permits remains a problem. The uncertainty and unpredictability in particular make it very difficult to plan and coordinate everything properly. It always gets sorted out in the end, but when exactly is anyone’s guess. In Wallonia, for example, we have a 40,000 m² project that has been on hold for two years. And even once work has actually started, all kinds of unexpected things can still happen. A nesting bird, a rare flower that suddenly appears …: that is enough to bring a construction site to a halt overnight. From a logistical and organisational point of view, that is far from straightforward.”

Charles Valcke: “We are also increasingly seeing projects that have already entered the construction phase being stopped. Clients and investors naturally want to get started as soon as possible, but if something does go wrong, the consequences are inevitably frustrating. PFAS is also a popular reason these days for temporarily halting projects. Unfortunately, we have also experienced first-hand how difficult the permitting process can be, specifically in connection with installing a wind turbine of our own at our site in Vlamertinge. Despite a positive opinion from the city authorities and around 120 letters of support from local residents, the permit was initially granted and then rejected on appeal. We now have to carry out additional bird surveys to potentially secure approval in a new permitting process. It is particularly frustrating when there is so much support for a project.” 

Maarten Allijns: “That unpredictability has to go. Simply knowing in advance how long the process will take, so that it cannot drag on indefinitely, would make a big difference. In the Netherlands, the permitting process is much clearer and fairer, with fixed time limits. You know in advance that you will get the go-ahead if your application meets all the stipulated conditions, and when you can start. More preparatory work is also involved, which helps the process run more smoothly. I think it’s a good system.”

Finally, if you could each change one aspect of industrial construction tomorrow, without any budgetary or regulatory constraints, what would it be?

Maarten Allijns: “As I mentioned earlier, clear timeframes and greater predictability in permitting processes. And, more broadly, a better balance between personal and collective interests. A single person or party raising objections is enough to torpedo a project with enormous social value. That doesn’t feel right. On the other hand, one thing we could do without here is grid congestion, as seen in the Netherlands. Problems with connection capacity could pose a serious threat in future, both to the delivery of new projects and to the economy in general.”

Luc Ysebaert: “We operate in six countries. That means six different ways of ensuring stability, fire safety and goodness knows what else. It would be a dream to achieve some degree of consistency and simplification at European level. At the moment, you have to build in a completely different way as soon as you cross a border.”

Charles Valcke: “There are indeed still some absurd differences in regulations. Take seismic zones, which suddenly stop at the French-Belgian border (laughs). It would certainly make sense to harmonise things a little better.”

Timothy Cuypers: “I would break away from the dullness of traditional industrial construction in favour of future-proof, attractive buildings that offer an engaging experience and can be adapted flexibly to new needs or requirements. All this would be made possible by flexible permitting, allowing not just developers but also architects, contractors and manufacturers to respond more quickly. That can only benefit the end customer …”    

Een zakelijke vraag aan Hercull? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
  • CompanyHercull
  • CompanyVandersanden
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.