Subcontracting from 1 January 2025. Are you ready?
Text Mathieu Malfait, BelexaImage Belexa

On 1 July 2024, the Act of 7 February 2024 on ‘Extra-contractual liability’ was published in the Belgian Official Gazette. This new Act, which will apply from 1 January 2025 to all events occurring from that date onwards, replaces the old rules on extra-contractual liability. For the legal experts among us, these are set out in Articles 1382 to 1386bis of the Civil Code.
As a contractor, you have a contractual relationship with your client on the one hand and your subcontractor on the other, so you might be inclined to think this new Act does not affect you. Is that right? Not quite, as we will explain below.
What is the current situation?
For now, the ‘Stevedores’ judgment’ of 7 December 1973 still applies. Applied to a situation involving client A, main contractor B and subcontractor C, this meant that it was quite difficult for client A to bring a claim directly against subcontractor C if the latter had committed an error in connection with the subcontract. This is why it was also referred to as the so-called ‘quasi-immunity of the performing agent’. On the one hand, there is no contract between client A and subcontractor C on which to base a contractual claim, while on the other hand, an extra-contractual claim is only possible if there has been a criminal offence or a fault causing damage that goes beyond the contract.
What changes from 1 January 2025?
This system will change from 2025. Under the new Act, parties to a contract can be held liable on both contractual and extra-contractual grounds. For example, client A and main contractor B will be able to bring claims against each other on both contractual and extra-contractual grounds. The same will apply to main contractor B and subcontractor C. There will still be no contract between client A and subcontractor C, of course, but it will now be much easier to bring an extra-contractual claim against the latter. There will no longer have to be a criminal offence or a fault causing damage that goes beyond the contract.
The protection afforded by quasi-immunity will therefore largely disappear, although contractual exceptions will still be possible. Hence the title of this article. Are you ready for this new legislation? Except in specific situations, namely harm to physical or mental integrity and intentional misconduct, you will be able to fine-tune various matters contractually.
For example, defences under the main contract (the contract between client A and main contractor B) and the subcontract (the contract between main contractor B and subcontractor C) will carry through. This means that subcontractor C, for instance, will be able to invoke a limitation of liability clause or an exemption clause against client A if it was included in the subcontract or main contract.
When subcontracting, it is therefore always advisable to ensure that the main contract and the subcontract are aligned, taking the specific circumstances into account.
Please do not hesitate to contact us if you need assistance or have any questions.