For a renovation or vertical extension, the structural engineering study starts with a question: what can the existing load-bearing structure still support? For BeHeCON, this is the starting point for integrating new functions and building elements into a building. The structural engineering firm calculates structures in concrete, steel, timber and masonry, and applies this expertise to the repurposing and extension of existing buildings.
“When a design combines an existing and a new situation, we model the load-bearing structure to determine overall and local stability under vertical and horizontal loads,” explains Bert Hertleer, engineer and managing director at BeHeCON. “This calculation model allows us to coordinate the new interventions with the existing structure as efficiently as possible. This helps us avoid additional demolition work or unnecessary strengthening of the load-bearing structure wherever possible.”

Surveying the existing structure
Reliable calculations first require a clear picture of what has actually been built. To this end, BeHeCON gathers existing plans and survey data, supplemented by destructive or non-destructive testing where necessary. Architectural plans based on a 3D scan can also help reveal discrepancies between the original plans and the current situation. The firm then assesses which elements can be retained and where strengthening or modification is needed. It also checks the structure against the required fire resistance and the standards for assessing existing buildings. “We aim to retain load-bearing structures in masonry, timber, concrete and steel wherever possible,” says Bert Hertleer. This approach can lead to a wide range of interventions. For a new storey, for example, it is necessary to determine what loads the existing structure and foundations can support. A roof garden places different demands on the floor beneath it, while new terraces need to be carefully anchored to the building. In addition to stability, these connections also need to incorporate thermal breaks to limit cold bridging.
Coordinating design and construction
The sequence of works can also be decisive. When existing stability cores are replaced by a new lift or stair core, the building must remain stable at every stage of construction. This requires a study of both the final structure and the temporary conditions on site. According to Bert Hertleer, this coordination should ideally begin during the preliminary design phase. BeHeCON then works with the client, architect and contractor to consider the location of load-bearing elements, the choice of materials and practical buildability. Acoustic, building services and EPB requirements are also taken into account. Retaining an existing load-bearing structure can reduce the need for new materials and the associated CO2 impact. At the same time, targeted interventions can simplify construction and keep costs under control. “We integrate structural engineering into the design without compromising the architecture,” concludes Bert Hertleer. “The best solution is one that is technically sound and practical to build.”