Wiegelied, Ostend | Pile foundations for a stable building

Wiegelied, Ostend | Pile foundations for a stable building

A stable building starts with solid foundations. In most cases, traditional foundations made from poured concrete are sufficient to ensure stability. But sometimes the ground structure does not have enough bearing capacity. In that case, pile foundations provide a reliable solution.

Overall, the coastal strip in West Flanders has less stable ground. Hence the need for pile foundations.

GVS piles were chosen for Wiegelied. To install this type of pile, De Waal Solid Foundations brought a 70-tonne piling rig to the site. During drilling, the soil is displaced sideways, after which the concrete is poured and the reinforcement installed. The variable parameters, concrete type, reinforcement, bore diameter and depth, are determined by the company’s own calculations based on the ground investigation. 

Achieving sufficient bearing capacity
De Waal is considerably more active in some regions than in others. Overall, the coastal strip in West Flanders has less stable ground. The same is true of Ostend. “We have carried out work there many times. In Koksijde, by contrast, to name another coastal town, we are less active. The ground there is better, so pile foundations are the exception,” says project manager Mike Blieck.

For every project, the load calculations in the structural design study provide the starting point for designing the pile foundations. Both end-bearing and friction resistance are calculated. For Wiegelied, the preliminary study resulted in a pile foundation comprising 53 piles with a bore diameter of 31/51 cm and a pile length of 9 metres. A substantial job. “To those unfamiliar with the work, it may seem very complex and extensive, but thanks to our years of experience and know-how, the pile foundations were installed without a hitch. This was also thanks to our client’s smooth co-operation and thorough site preparation.”

For every project, the load calculations in the structural design study provide the starting point for designing the pile foundations.

Belgium’s largest player
De Waal Solid Foundations was formed at the end of June 2017 through the merger of De Waal Palen, Wig Palen and Olivier Funderingstechnieken. The three companies pooled their experience and expertise to strengthen their market position. The company is a leading force in foundation engineering in Belgium.

Mike Blieck: “We have actually been active in the sector since the 1960s. The merger means we can now offer our clients even more options. We have a large, modern fleet of machinery. Our divisions complement one another, while also allowing us to specialise further. That makes us a stronger company.”  

Words Stephanie Demasure    |    Photography Olivier Rens

Question about this story? Ask your question

Who worked on Wiegelied

  1. ClientStad OostendeMentioned in Wiegelied | Ostend
  2. architectBAST architects & engineersMentioned in Wiegelied | Ostend
  3. main contractorFurniboMentioned in Wiegelied | Ostend
  4. main contractorPUUR BouwenMentioned in Wiegelied | Ostend
  5. Houten binnenschrijnwerkHolvoet GebroedersMentioned in Wiegelied | Ostend

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectWiegelied
  • SubjectHealthcare projects
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.