Renovation work is in full swing at the Brouckère underground car park in the heart of Brussels. The project presents a number of logistical challenges, as well as a novel technique. “We invested in a powerful pump to lay the screed as efficiently as possible,” says project manager Gert Ulrichts. 

The brief set by client Interparking was clear: a complete structural renovation of the Brouckère underground car park. “This was not unfamiliar territory for us, as we have renovated several car parks in Antwerp for this client in recent years,” says Gert Ulrichts of contractor Renotec. “Interparking regularly carries out maintenance or renovation work on its car parks when issues such as concrete cancer or other problems arise. At Brouckère, we started work in November 2020, focusing mainly on structural repairs. We are working on three floors, specifically levels -2, -3 and -4.”

“We began by replacing the damaged floor slabs,” Gert Ulrichts continues. “In some areas, we removed entire sections, then reinforced, shuttered and poured them again. On levels -2 and -3, we also milled off the top centimetre of concrete, as this layer had been most severely affected by chlorides and carbonation. The beams on levels -2 and -3 were repaired as well. We completed these structural works, carried out in seven phases, in August 2021.” 

“In this case, the saying ‘well begun is half done’ really does ring true,” stresses Gert Ulrichts.

15,000 m² of fire protection

Since then, Renotec has been making good progress with the reinstatement work. Gert Ulrichts: “A new screed is being laid using Sika mortar. We milled off 1 cm and are applying a new 2 cm layer on top to create an even finished floor. Once the new screed is in place, we will also install waterproofing and apply fire protection to the ceilings and beams. This covers a total area of around 15,000 m². The floor will also be thoroughly cleaned. We expect to complete our work by the end of spring. Another contractor will then install the electrical and sprinkler systems, and the stairwell, which was not part of our scope, will also be renovated.”

“We opted to purchase a powerful Inotec machine to use with Sika products supplied in big bags,” says Gert Ulrichts.

A new pump

Renotec’s commitment to innovation and new techniques is also clearly demonstrated in this project. “The screed was laid using a new system developed by Sika in collaboration with machine specialist Inotec. Rather than using traditional repair mortar in the conventional way, we chose to purchase a powerful Inotec machine and use it with Sika products supplied in big bags. We are the first contractor in Belgium to have purchased this type of pump for laying mortar in this way. It is an investment that significantly boosts efficiency and will certainly prove useful on future projects too. We also brought our established expertise to bear on this project, from local concrete repairs and floor slab replacement to installing bonded reinforcement with slot-in plates and applying fire protection.”

All damaged floor slabs were replaced or repaired in seven phases.

A project tailored to the job

For specialist contractor Renotec, this is a renovation project tailored to the job. “But it is certainly challenging, particularly from a logistical point of view,” explains Gert Ulrichts. “We are working underground in central Brussels, in the European Quarter, while another contractor is carrying out a construction project above us. That means two contractors on the same site, sharing the same limited access. There is very little room for deliveries, storage and containers, so planning was crucial. For example, 400,000 kg of mortar had to be delivered, amounting to four hundred big bags and around twenty deliveries. That was only possible with careful planning and coordination.” The mission has been accomplished, as the project remains firmly on schedule. “In this case, the saying
‘well begun is half done’ really does ring true. That is one of our strengths, along with our leading role in techniques and materials, as we are demonstrating here with this innovative flooring system. We aim to deliver quality and efficiency on every project, and we are always prepared to make the necessary investments,” concludes Gert Ulrichts.    

Question about this story? Ask your question

Who worked on it

De Brouckèretoren in Brussel

  1. ownerWhitewood
  2. property developersDW Partners, LP
  3. architectCONIX RBDM Architects
  4. contractorCordeel
  5. demolition worksDe Meuter
  6. asbestos removalRenotec
  7. engineering consultancyKiwa Oesterbaai
  8. clientInterparking
  9. clientImmobel Group
  10. architectCONIX RDBM Architects
  11. main contractorCordeel Group

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectDe Brouckèretoren
  • SubjectConcrete and steel construction
  • CompanyInterparking