Precast concrete façade speeds up construction of Amsterdam residential tower

Text Joke HofmansImage Tim Fisher en Loveld

The Ensemble is een nieuwe blikvanger in Amsterdam-Zuid.
The Ensemble is een nieuwe blikvanger in Amsterdam-Zuid.

Loveld, the Aalter-based manufacturer of precast architectural concrete, seems to be a familiar sight in Amsterdam. Alongside the Fortitudo and Caritas towers, The Ruby, The Jay and the Brinktoren, the company recently helped deliver a fifth residential tower: The Ensemble. But how can a specialist in architectural concrete play the leading role in a building with a brick façade? We put that question to Project Sales & Development Manager Vincent Termote.

Between the Johan Cruijff ArenA and Nelson Mandela Park stands The Ensemble, a new landmark in Amsterdam-Zuid. The two residential towers provide 592 rental homes and almost 20,000 m² of office space. The complex’s low-rise section houses restaurants and cafés, a pharmacy, a youth talent centre and a fitness centre. The Ensemble is one of the most sustainable buildings in the Netherlands, with an EPC rating of A++++, 100% renewable energy and a BREEAM sustainability certificate at the highest level.

The façade panels also incorporate electrical wiring, waterproofing and rainwater drainage.

Bricks encased in concrete

Vincent Termote: “People usually associate Loveld with façades in shot-blasted, acid-etched, polished and coloured concrete. But alongside these high-quality finishes, other materials can also be incorporated into precast concrete elements, such as natural stone, ceramic tiles or brick slips. The brick slips are laid at the bottom of the formwork, and we pour concrete into the mould over them, so that the bricks are completely ‘embedded in concrete’.”

“Why precast concrete? At great heights, bricks cannot be bonded in place because there is a risk that they may eventually come loose. So, for Tower 2 of The Ensemble, we encased all the brick slips in concrete. What is special is that the balconies are also completely clad in bricks, even the underside of the floor slab. Some ceilings inside the building are also clad in brick slips.”

Installation on site took just eight days per floor.

Architectural freedom through prefabrication

The façade elements are manufactured not on site, but in Loveld’s workshops. Every element and every brick slip is drawn in 3D. The formwork is then made. Vincent Termote: “Would you like to incorporate a logo or relief into your façade cladding? Or use a special brick bond? No problem. Prefabrication makes more complex brickwork possible. We don’t have to work at height in our workshops, but simply lay the façade panels flat.”

Shifting work from site to workshop

Prefabrication for The Ensemble went even further. Loveld also incorporated electrical wiring, waterproofing and rainwater drainage into the concrete elements. Even the windows were fitted into the façade elements before everything was sent to the construction site. Vincent Termote: “With prefabrication, most of the work is done in advance, and that brings major benefits,” explains Vincent Termote. “We’re not dependent on the weather, and because quality checks are carried out beforehand, there are hardly any surprises or mistakes on site. That saves a huge amount of installation and construction time.”

All the tower’s balconies are also fully clad in bricks.

Less impact on the surrounding area

That is good news not only for the client, but certainly for the surrounding area too. “The disruption caused by traditional construction on projects of this scale is often considerable and varied,” says Vincent Termote. “In Belgium, too little attention is still paid to this, meaning people sometimes have to live next to a construction site for two to three years. Thanks to prefabrication, we were able to complete a floor in just eight days.

Mind-boggling figures

  • Loveld used 507,622 bricks
  • The 100-metre-high tower has 137 balconies
  • The tower contains almost 2,000 m³ of grey concrete
  • The heaviest precast façade element weighed 20,700 kilograms
  • A total of 237 types of façade element had to be fitted together on site

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectYearbook
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.