Yearbook

Spectacular retaining wall works for Middelkerke’s new casino

Lameire voerde de beschoeiingswerken voor de kelderverdieping van het nieuwe casino van Middelkerke uit met cutter soilmixing.
Lameire voerde de beschoeiingswerken voor de kelderverdieping van het nieuwe casino van Middelkerke uit met cutter soilmixing.

Anyone who has seen the stunning design will agree: Middelkerke’s casino is set to become the Belgian coast’s landmark attraction. The grand opening is not scheduled until the end of 2023, but the earthworks and foundation works are now virtually complete. In recent months, they have made for spectacular scenes, including a construction pit several metres deep and imposing piling rigs. Lameire Funderingstechnieken once again delivered first-class workmanship, installing robust retaining walls around the construction pits for the casino building and underground car park. “The project was very challenging, both technically and logistically,” says project engineer Nicolas De Pestel.

Preparatory work on the new Middelkerke casino began at the end of January. The scope was considerable: large-scale demolition, excavation and earthworks, installation of a new sewerage system, a new foul-water and rainwater drainage system and, last but not least, retaining walls for the imposing construction pits for the casino building and the two-level car park beneath the future green promenade, into which the new casino will be seamlessly integrated. TM Casino Furnibo-Democo called on Lameire Funderingstechnieken to carry out the retaining wall works. Part of the 2Fund group, the company specialises in deep foundation and retaining wall techniques for private clients, industry and infrastructure projects. “Flexibility is one of our key strengths, so this project was right up our street,” says Nicolas De Pestel. “To meet the tight schedule, we were able to deploy several machines at the same time and maintain a very high rate of progress. On sites like this, where timing is crucial, that is a significant advantage.”

Part of the soil-mix wall is not protected by the existing sea defences. At that point, it is therefore almost twice as thick: 100 instead of 55 centimetres!

Cutter soil mixing

The first phases of the project were immediately the most demanding. Lameire carried out the retaining wall works for the casino basement using cutter soil mixing. “A soil-mix wall is a retaining wall that limits the passage of soil and water and consists of a continuous series of soil-mix panels. These panels are made from a mixture of soil, water and cement. We have been specialising in soil mixing for several years and are among the pioneers of this technique in Belgium,” explains Nicolas De Pestel. “In that first phase, we built around 430 metres of soil-mix wall, approximately 15 metres deep. It was a race against time, because dewatering and excavation started as soon as the pit was enclosed. We were also certainly challenged from a technical point of view. Part of the soil-mix wall is not protected by the existing sea defences and can therefore be fully exposed to wave action. As it has to withstand the notorious thousand-year storm, we decided to make it almost twice as thick at that point: 100 instead of 55 centimetres!”

“To meet the tight schedule, we were able to deploy several machines at the same time and maintain a very high rate of progress,” says Nicolas De Pestel.

Combined with secant pile walls

Lameire also used soil mixing for part of the second phase of the retaining wall works, installing 15-metre-deep retaining walls around the excavation for the underground parking wings on either side of the casino basement. Inland, beside the tall apartment buildings on the sea dyke, concrete secant pile walls were chosen to minimise deformation. “Because those apartment buildings are only 8 metres away, we needed a stiffer retaining wall there. On the seaward side, the allowable deformation was slightly greater, so we could use soil mixing again. The retaining walls had to connect seamlessly with those around the casino basement. In this way, we formed the outline of a 300-metre-long parking structure, approximately 15 metres wide,” says Nicolas De Pestel. “In this second phase, which took place in the autumn, it was mainly the logistics coordination and measures to minimise disruption that gave us a few headaches. Among other things, we had to ensure that the fire brigade could access the neighbouring apartment buildings at all times, as they can only be reached via the sea dyke, while working space was very limited. No easy task, with an 8-metre-deep construction pit just a few metres away. In terms of both planning and technical complexity, this was no ordinary project! We are now installing the ground anchors, the final stage of our work. We should be finished by the end of 2022, after which construction of the car park can get under way in earnest!”    

Een zakelijke vraag aan Lameire Funderingstechnieken? Get in touch

Wie aan Casinogebouw werkte

  1. casino and hotel designOZMentioned in Middelkerke to get iconic casino building and beautiful stretch of dune landscape back
  2. Executive architectBureau BouwtechniekMentioned in Middelkerke to get iconic casino building and beautiful stretch of dune landscape back
  3. contractorFurniboMentioned in Middelkerke to get iconic casino building and beautiful stretch of dune landscape back
  4. contractorDemocoMentioned in Middelkerke to get iconic casino building and beautiful stretch of dune landscape back
  5. beschoeiingswerkenLameire FunderingstechniekenIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectCasinogebouw
  • SubjectYearbook
  • CompanyLameire Funderingstechnieken
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.