Oak Park residential project: less disruption with Smeyers’ groundwater reinjection system

Tekst Niels RouvroisBeeld Smeyers

Een retourbemaling zorgt ervoor dat het lozingsdebiet beperkt blijft.
Een retourbemaling zorgt ervoor dat het lozingsdebiet beperkt blijft.

Development of Oak Park, a residential project in Sint-Amandsberg, is well underway. The distinctive complex is set in a beautiful green inner area next to Potuitpark, giving future residents the chance to live close to nature. Groundwater control specialist Smeyers, part of Aertssen Group, was brought in to manage the dewatering works. “To limit the environmental impact, a groundwater reinjection system was chosen,” says Bert Creve of Smeyers.

Respect for nature will be visible and tangible not only in the finished project. The local flora and fauna are also being taken into account during the dewatering process.

The two small-scale residential buildings will together provide 31 high-quality park apartments with one, two or three bedrooms, all equipped with convenient home automation. Oak Park is committed to sustainability without compromise. The nearly zero-energy apartments, with an E-level of 30, fully meet current EPB standards. Light and openness are a recurring theme in the design of every apartment. With just four storeys and carefully chosen materials, the buildings blend harmoniously with the existing greenery.

Respect for nature will be visible and tangible not only in the finished project. The local flora and fauna are also being carefully considered during construction. Bert Creve explains: “When carrying out dewatering in an area like this, it is very important to minimise the impact on the surrounding area as much as possible. This can be achieved with a groundwater reinjection system, in which the pumped water is injected back into the ground elsewhere. Water is extracted from the excavation using deep wells. A preliminary study determines the zones in which the pumped water must be reinfiltrated.”

Groundwater control specialist Smeyers was brought in to manage the dewatering works.

Limited discharge rate

A groundwater reinjection system keeps the discharge rate down. “By staying within the specified limits, you can carry out the works under permit class 3 thanks to a reinjection system,” explains Bert Creve. “Naturally, the groundwater must also meet a certain quality standard before it can be injected back into the ground. These parameters are set out in VLAREM, and the standards are quite strict. That is why reinjection is not possible on every site. The volume to be reinjected is also determined in advance, and the system is configured accordingly. In this case, between 90 and 100 cubic metres per hour are being pumped back into the ground.”

Another benefit of groundwater reinjection is that it prevents ground settlement and the potential inflow of contamination from the surrounding area. A total of nineteen reinjection wells were installed for Oak Park, injecting water to a depth of 32 metres, along with around fifteen extraction wells in the excavation, reaching a depth of 17 metres. Bert Creve says: “Monitoring wells on site track the calculated groundwater levels, while pumping depths, flow rates and pipeline pressure are monitored extensively, 24/7. The pump systems are also switched on and off remotely.”

A total of nineteen reinjection wells were installed for Oak Park, injecting water to a depth of 32 metres, along with around fifteen extraction wells in the excavation, reaching a depth of 17 metres.

Environmental considerations

The works are carried out under the supervision of an arborist, who helps keep the impact on the surrounding nature to an absolute minimum and maintain soil moisture levels. Local residents are involved too. “They were informed about heat stress in plants so they can raise the alarm if they notice any problems. A pumping station and buffer tank were also installed as part of the dewatering system, allowing residents to draw water to irrigate the surrounding area. This project pays particular attention to its environmental impact, which we, as a groundwater control specialist, can only welcome. Groundwater is one of our most precious resources and must be managed with great care. That is why Smeyers is always looking for new and improved solutions within its field to address the climate challenges we face,” concludes Bert Creve.    

Een zakelijke vraag aan G. Smeyers N.V? Neem contact op

Bedrijven in dit verhaal

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectOak Park
  • OnderwerpConstruction projects
  • BedrijfG. Smeyers N.V
Deel dit artikel

Volgen op Bouwen aan Vlaanderen

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.