Willemen office building | Hasselt

Willemen office building | Hasselt

Willemen’s Limburg base completed in record time

The new Limburg headquarters in Hasselt marks the definitive integration of former Kumpen into Willemen Groep and the establishment of Willemen Construct and Willemen Infra. The contractors involved immediately shifted into top gear and delivered the complex fully finished after just eight months. This was a unique achievement, made possible in part by excellent project preparation, outstanding collaboration between all the parties involved in the work, and the extensive use of Lean and BIM.

De bovenverdieping met privéwoning, dakterras en groendak.

The impressive entrance sets the tone straight away.

The merger of Kumpen and Willemen Groep made headlines in the construction industry. This was especially because it led to the much-discussed merger of Kumpen’s construction division and Willemen General Contractor (see box), resulting in the establishment of Willemen Construct. This new player in the construction market has recently moved into an ultra-modern facility in Hasselt, alongside Willemen Infra (formed by the merger of Aswebo, Aannemingen Van Wellen and Kumpen’s infrastructure division) and Kumpen Renovation Techniques (formerly Kumpen’s sewer and water-main renovation division, which continues to operate under the name Kumpen). “The new office building had been in the pipeline for quite some time, but naturally the developments behind the scenes gave it extra significance,” says Wim Briels, project director at Willemen Construct. “We considered all kinds of options, including a complete renovation of the former building, and visited several potential locations. In the end, however, we decided to build the new facility literally and figuratively a stone’s throw from our existing headquarters. It took several years to make the final decision, but in hindsight the timing was ideal: the new building, now the Hasselt offices of Willemen Construct and Willemen Infra and the headquarters of Kumpen Renovation Techniques, was completed a few months after the merger. The project therefore symbolises the new direction our organisation is taking.”

A remarkable feat

Een grote open ruimte met industriële afwerking in de details.

All the staff have lunch together in the spacious canteen.

It is therefore no surprise that expectations were exceptionally high from the outset. By delivering the building just over eight months after the first spade went into the ground, Willemen Construct and the subcontractors involved made an impressive calling card. “We began the preparatory work in early 2018, and in April we started excavating the construction pit. By the summer break, the shell was wind- and watertight; practical completion took place on 30 November, and just before the Christmas break we all moved in,” explains Wim Briels.  

Willemen Construct did not, of course, carry out the entire project alone. “Our colleagues at Willemen Infra
built the access road, including the landscaping,” Briels continues. “Together, we used every means available and applied a range of innovative methods and techniques to complete the work as quickly as possible. The extensive use of Lean and BIM was an important ingredient in our recipe for success, but the construction planning was just as crucial. As an experienced contractor, we know all the potential obstacles and understand exactly why most projects run late. Even moving a wall can have a huge impact, so all the key decisions had to be made before we started work, allowing us to focus largely on progress meetings afterwards. The precast concrete structure, including the stair cores, the joinery … everything was made to measure and was largely ready when the basement slab had been poured and the structural work could begin. ‘A remarkable feat’ is certainly an apt description.”  

A tightly managed Lean schedule

De bar van de feestzaal past in het harmonieuze kleurenpalet.

To complete the building within the set timeframe, the contractors followed a very tightly managed Lean schedule. “An important first step was selecting the subcontractors, prioritising quality and reliability over price,” says site manager Julian Dullers. “We then drew up detailed six-week schedules with all the parties, filling in each day’s work and setting out several key milestones. Every morning, I went through the schedule with the relevant foremen to check whether we were still on track, whether there were any issues on site, what could be improved, and so on (daily stand-up). If any clashes came to light, we tried to find a solution straight away. This meant that our construction partners felt much more involved and committed, and took greater responsibility. They thought not only about their own work, but also about the work of the teams before and after them. They took pride in sticking to the schedule and saw it as a great compliment to be able to contribute. The fact that they already knew one another from previous projects and were willing to go the extra mile when needed meant that many issues practically resolved themselves, allowing us to focus our daily meetings on fundamental matters. This close collaboration really paid off, and the project went extremely smoothly.”   

Advanced BIM applications

Kantoorgebouw Willemen   Hasselt

The central courtyard, with its green wall, gives the new office building a distinctive character.

Lean played an important role not only during construction but also throughout the design phase. “By applying Lean engineering and carefully translating everything into a detailed BIM model, we were able to finalise the design on time and efficiently. Flexibility was central, as were minimising the environmental impact and reducing energy consumption. Rainwater harvesting, LED lighting that adjusts automatically to daylight levels, solar shading controlled by a weather station for each façade, an air-to-water heat pump and climate ceilings that maintain a
comfortable indoor climate, and on-site electricity generation using solar panels … it all fits perfectly with the innovative vision we had in mind,” says Briels. “Our BIM team also had plenty of scope to put its skills to use. They surveyed the site with a 3D laser scanner, which produced highly accurate 360° images and a detailed point cloud, forming the basis for the shared 3D model. All our colleagues were able to visit their future workplace virtually, while 4D simulation allowed us to visualise the site layout and safety provisions.”  

Simplicity and restraint

De imposante voorgevel wordt ondersteund door slechts drie betonnen zuilen.

The first and second floors are given over to meeting rooms and open-plan offices, interspersed with enclosed ‘bubbles’ where staff can hold meetings or make phone calls in private.

The extensive use of Lean and BIM meant that the structural shell went up in no time. After the summer break, the subcontractors had four months to complete the entire building. Simplicity and restraint were the guiding principles. “To avoid jeopardising the tight schedule, we opted for dry construction, with raised floors, suspended ceilings and plasterboard and demountable partition walls, rather than screed and plastering. Some concrete features have been left visible here and there, which is fitting for a construction company like ours. The façade is clad in sand-coloured brick slips,” Briels explains. “The 1,000 m² basement contains several parking spaces, a bicycle store, showers, a server room … The ground floor accommodates reception, administrative areas, including offices for management, accounts and IT, meeting rooms and a large cafeteria. In the centre of the building are two stairwells and a lift core. The first and second floors are reserved for meeting rooms, including a dedicated Lean meeting room on each floor, and open-plan offices designed for flexible working, interspersed with enclosed ‘bubbles’ where staff can hold meetings or make phone calls in private. Each floor also has a kitchenette opening onto a central courtyard with a green wall. We are certainly pleased with the result. We are still amazed that it took us just eight months to deliver our office from start to finish. It is further proof that we can rise to even the most complex challenges!”  

Willemen Construct, Willemen Infra and Kumpen Renovation Techniques

Kantoorgebouw Willemen Hasselt

After Willemen Groep acquired a 50% stake in Kumpen nv in 2011, it bought the remaining 50% of the shares on 1 July 2018. This was accompanied by the establishment of Willemen Construct, formed through the merger of Willemen General Contractor and Kumpen’s construction division. Willemen Construct is headquartered in Mechelen, but since the start of this year the newly formed construction company has also had a branch in Hasselt. Aswebo, Aannemingen Van Wellen and Kumpen’s infrastructure division have also merged to form Willemen Infra, which likewise has premises in the new Hasselt office building. It shares a floor there with Kumpen Renovation Techniques, which specialises in water-main and sewer renovation. This was one of the former Kumpen’s activities, so the division continues to operate under that name. “Kumpen was one company with several activities, but since its integration into the Willemen structure, those specialisms have been assigned to various entities. The Hasselt branch is the only one within Willemen Groep to bring together several entities at a single location,” the company says. “The merger strengthens Willemen Groep’s position as one of Belgium’s largest family-owned construction groups, driven by efficiency and innovative technologies,” says Tom Willemen, CEO of Willemen Groep. “Willemen Construct joins the ‘construction’ business line, while Willemen Infra and Kumpen Renovation Techniques join the ‘infrastructure’ business line. The construction and infrastructure business lines are, in turn, part of the ‘general contracting’ cluster. Through this organisation into clusters and business lines, we aim to create efficient synergies, remove unnecessary barriers and establish an even clearer profile for ourselves in the competitive construction market.”

Question about this story? Ask your question

Who worked on it

Kantoorgebouw Willemen Hasselt in Heusden-Zolder, nieuwbouw

  1. contractorWillemen Construct
  2. toegangsweg, inclusief de omgevingsaanlegWillemen Infra

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectKantoorgebouw Willemen Hasselt
  • SubjectConstruction projects
  • CompanyWillemen Construct
  • CompanyWillemen Infra
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.