The Covid-19 virus and construction contracts

The Covid-19 virus and construction contracts

The coronavirus and the government measures to prevent the further spread of the virus have had far-reaching consequences for the economy and for businesses. The future also looks uncertain. Could the ‘1.5-metre economy’ become the new reality? The coronavirus crisis has also had a serious impact on the carrying out of construction work. Many contractors and subcontractors who are unable to meet their contractual obligations will cite the coronavirus crisis. It will then be for the court to determine, in each individual dispute, whether force majeure has in fact occurred.

Pacta sunt servanda. The rule is that agreements have the force of law between the parties. If a contract is not properly performed and the cause of this non-performance lies in the fault or negligence of one of the contracting parties, that party is liable and must compensate all the loss caused by its wrongful act or negligence.

However, if circumstances arise after a contract has been concluded that make it temporarily or permanently impossible to perform the agreement, force majeure occurs. In such cases, the debtor is not at fault or negligent, but is itself the victim of events that pose an insurmountable obstacle to the performance of an obligation under the agreement. In cases of force majeure, the debtor is no longer required to perform its obligation.

Force majeure is defined in two articles of the Civil Code. Article 1147 provides that a debtor is ordered to pay damages for failing to perform an obligation, including by delaying performance, unless it proves that the non-performance resulted from an external cause for which it cannot be held responsible, and that it was not acting in bad faith. Article 1148 provides that no damages are payable when the debtor has been prevented by force majeure or accident from giving or doing what it was obliged to give or do, or has done what it was prohibited from doing.

These two articles show that force majeure occurs in the event of an unforeseeable event beyond the control of the parties that makes performance of the agreement temporarily or permanently impossible.

Anyone wishing to invoke force majeure must also prove that force majeure has in fact occurred. As a rule, the contractor must demonstrate that it made every effort that could reasonably be expected to perform its obligations correctly. A contractor cannot simply throw in the towel in advance.

The coronavirus crisis certainly does not reverse this burden of proof and will therefore never be accepted as giving rise to a presumption of force majeure. In certain cases, the coronavirus crisis may make contracts temporarily, and sometimes even permanently, impossible to perform. Force majeure applies only in these cases.

When considering the effect of the current coronavirus measures on the carrying out of construction work, a distinction must be made between indoor and outdoor work.

Construction work indoors is no longer permitted in homes where people are living. This is the rule, with an exception only for urgent repairs that are also necessary for safety, wellbeing or hygiene. Construction work may still be carried out indoors in unoccupied buildings, flats or houses under construction. Construction work outdoors is also permitted.

In these latter two cases, however, social distancing measures must be strictly observed. These measures naturally have a major impact on the carrying out of the work. For example, only a limited number of workers may be on a site at any one time. This means, of course, that more time will be needed to complete certain works. The transport of workers must also be organised differently. It is recommended that this be limited to one person per vehicle. In vans designed to carry four or five people, a maximum of two people may travel: the driver and one passenger, seated in the back (that is, in the seat diagonally behind the driver). Larger minibuses may carry a maximum of four people on this basis, provided that the minimum distance of 1.5 to 2 metres between them is maintained at all times.

Of course, every contractor remains dependent on the supply of construction materials. A contractor also needs to be able to work. If production of these construction materials comes to a halt, the contractor will no longer be able to carry out even the permitted work.

For contracts concluded before the coronavirus measures were issued, it will therefore always be necessary to assess each contract individually to determine the extent to which these measures have actually affected the carrying out of the work. If the measures have had no impact, the debtor in default will not be able to invoke the coronavirus crisis as force majeure. The burden of proof lies with the party invoking force majeure. 

The position is, of course, different for contracts concluded after the introduction of the coronavirus measures concerning social distancing. These measures were known when the contracts were signed, so their impact on performance of the agreement can never be invoked as force majeure. Anyone entering into a contract now must therefore take account of the impact of the coronavirus measures on its performance.

Even when the coronavirus measures are relaxed or lifted, new contracts should address the consequences of a possible further wave of the epidemic. Scientists are now convinced that the coronavirus will not simply disappear and that it may strike again at unpredictable times. Since this is a widely recognised possibility, account should be taken of its potential impact on the performance of an agreement.

It is therefore advisable to give due consideration in new contracts to the effects of force majeure on the performance of an agreement. An epidemic is no longer merely hypothetical. If the parties address this issue adequately when concluding the contract, they can build in legal certainty, giving all parties clarity even in a time of crisis. That legal certainty is currently lacking.

The parties can avoid this uncertainty by including a force majeure clause in an agreement, specifying precisely which circumstances will or will not constitute force majeure. If they do not, uncertainty will arise again and the parties will place their fate in the hands of the judge, who will decide whether or not particular circumstances constitute force majeure.

In uncertain times, many problems can therefore be avoided with a watertight contract that includes, among other things, a complete description of the rights and obligations of all parties, the various force majeure situations that may arise and their consequences for the performance of the agreement. Today, a contract must contain more than just a price and a subject matter. The contracting parties hold the key, since they are free to draw up their agreements as they see fit.

The current crisis has taught us that nothing is certain and that the world may look completely different again tomorrow. Anyone who fails to give sufficient attention to drafting their agreements is therefore no longer acting as a prudent person would.   

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectThemes
Share this article

Advertisement

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.