Quartier Bleu, Hasselt | 400,000 m³ of earthworks along Hasselt’s Kanaalkom

Quartier Bleu, Hasselt | 400,000 m³ of earthworks along Hasselt’s Kanaalkom

At 35,000 m², the Quartier Bleu excavation was the largest in the whole of Limburg for a long time. Between 24 February and 1 November 2016, no fewer than 400,000 m³ of soil was moved. “Since most of the broken-up paving was recycled and reused on site, and all the excavated soil was transported away by ship, there was hardly any disruption to the surrounding area. Given the substantial reduction in CO2 emissions, we can confidently call this a model project,” says Steven Lisens of Hasselt-based Baldewijns, which carried out the earthworks and demolition work.

With Baldewijns’ head office just a few kilometres away, the renowned family business was very much on home ground at the Quartier Bleu site. Working with Smet, which took care of the retaining wall (using secant piles) and dewatering of the excavation, Baldewijns excavated the soil layer by layer, drilling a series of anchors into the ground behind the retaining wall after each layer. The anchors were then grouted and tensioned. “Given the extremely tight schedule, the coordination between the retaining wall work and the earthworks required meticulous planning,” says Steven Lisens, director at Baldewijns. “Quartier Bleu has three underground floors, so the excavation was around 12 metres deep. It was a real race against time to complete the excavation within the set schedule.”

Dumpers deposited the excavated soil into a ship, using a temporary 21-metre-long steel bridge over the adjacent road.

A staggering volume

Excavating the construction pit was, in both the literal and figurative sense, a major undertaking. All told, a staggering 400,000 m³ of soil was involved. “But before we could actually start digging, we first had to break up the existing car park, remove the underlying foundation structures and take out the utility pipes, including the old
sewer system serving the city of Hasselt. The broken-up paving was recycled on site using a mobile crushing plant,” Lisens explains. “Because of the heterogeneous nature of the subsoil, we had to approach the excavation work with great care. First, we remediated and removed the heavily contaminated areas separately. We then loaded and screened the clean and slightly more contaminated soil separately.”

Transport by ship

Dumpers deposited the excavated soil into a ship, using a temporary 21-metre-long steel bridge over the adjacent road. Baldewijns handled an average of 3,000 m³ per day, rising to 4,500 m³ at peak times. “To increase the loading capacity of the 110-metre-long inland vessels, we had first dredged the Kanaalkom to a greater depth and created a temporary mooring structure using driven tubular piles. Transporting the excavated soil by ship saved us 250 lorry journeys a day, around 30,000 in total. This allowed us to keep disruption to the surrounding area to an absolute minimum and significantly reduce the project’s environmental footprint.”    

Question about this story? Ask your question

Wie aan Quartier Bleu werkte

  1. architectDe Gregorio & PartnersMentioned in Quartier Bleu, Hasselt | Pushing boundaries, literally and figuratively
  2. grond- en afbraakwerkenBaldewijnsIn this story
  3. electrical installationElektriciteitswerken JanssensMentioned in Quartier Bleu, Hasselt | Ingenious control systems for electrical installations, fire detection and access control
  4. engineering consultancyMACOBO-STABOMentioned in Quartier Bleu, Hasselt | Significantly lower costs thanks to technical and structural optimisations
  5. contractorTHV Houben-STRABAGMentioned in Quartier Bleu, Hasselt | Significantly lower costs thanks to technical and structural optimisations
  6. projectstenenNelissen SteenfabriekenMentioned in More than a million bespoke bricks for Quartier Bleu
  7. architectACPVMentioned in More than a million bespoke bricks for Quartier Bleu
  8. branddetectie-installatieKingspanMentioned in Impressive fire detection system for Quartier Bleu
  9. elektrotechniekenJanssens ElektriciteitswerkenMentioned in Impressive fire detection system for Quartier Bleu

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectQuartier Bleu
  • SubjectConstruction projects
  • CompanyBaldewijns
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.