Strength in numbers, added value

P+R Linkeroever is a unique car park, not only in its appearance and layout. Its building services also put it among the best in its class. VINCI Energies’ Total Technical Solutions approach, with ITB working closely with Cegelec, TranzCom and VINCI Facilities, delivered a state-of-the-art solution defined by integration, safety and sustainability.
108 cameras, 1,255 sensors indicating which parking spaces are available, 225 motion detectors, 10 kilometres of cable tray, thirteen low-voltage switchboards, 1,011 fire detectors, 72 sirens, 1,000 kVA of electric charging capacity, 125 charging points (with the basic infrastructure to expand to 750), 4G/Astrid, an electronic parking management system, 91 fire hose reels,
78 fire extinguishers and a fire pump with a capacity of 200 m³/h at 11 bar: P+R Linkeroever has become a technological tour de force.

High-tech, sustainable and safe
ITB looks back on this project with particular pride as the main building services contractor. “P+R Linkeroever was always going to be a challenging project,” says project manager Christophe Van den Bossche. “Its sheer diversity brought considerable complexity. Yet it is precisely on projects like this that we can make a difference. As part of VINCI Energies Belgium, we have access to a vast pool of knowledge and expertise in areas beyond our core business. What’s more, bringing our expertise together under one roof always leads to better integration. In this project, that approach enabled us not only to deliver outstanding technology, but also to achieve an exceptionally sustainable and safe result.”
ITB was responsible for the electrical installations and for coordinating all the building services work. Cegelec was brought in to handle plumbing, HVAC and the fire hose reels. TranzCom was responsible for ensuring the building complied with the regulations for ASTRID and 4G. “Once the car park is operational, a fourth VINCI Energies business will also come on board,” says Christophe Van den Bossche. “VINCI Facilities will be responsible for maintaining both the building and its technical installations.”
Question about this story? Ask your question
Who worked on P+R Linkeroever
- main contractorITBIn this story
- ASTRID en 4GTranzComIn this story
- maintenanceVINCI FacilitiesIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectP+R Linkeroever
- SubjectConstruction projects
- CompanyITB
- CompanyTranzCom
- CompanyVINCI Facilities